ASI (architect's supplemental instruction)

An ASI, short for architect's supplemental instruction, is a written instruction from the architect that clarifies the design or makes a minor change during construction. By definition it is not supposed to change the contract price or the contract time.

Last updated

What an ASI is

Architects use an ASI to fix small things quickly: a corrected dimension, a revised detail, a paint color, a clarified note. It often comes with revised sheets or sketches. The contractor is expected to carry it out.

The catch is the words no change in price or time. If the contractor believes the instruction does add cost or days, the contractor has to say so in writing, usually before doing the work and within the notice period in the contract. The ASI then turns into a change order request.

An ASI on a real job

An ASI arrives moving a row of light fixtures two feet to clear a duct. The electrician has not roughed in that area yet, so it costs nothing, and the crew simply builds from the new sketch. A second ASI the same week changes the lobby floor tile to a larger, thicker stone. The tile subcontractor sees that the new material costs more and needs a different setting bed. The project manager writes back the same day that this ASI has a cost impact and sends pricing.

Common mistakes with ASIs

ASIs and Trakend

Trakend does not have a separate ASI log. Contractors handle ASIs with the tools around it. Revised sheets are uploaded to the plan set and become the current revision, with the older one kept in the sheet's history. The ASI itself is stored in the project's files. If it has a cost, it is priced as a change order, and a question about it goes out as an RFI. See drawing revisions and change orders.

Related terms

Before the contract, the same kind of correction is an addendum. When an instruction changes cost or time it becomes a change order. An ASI is often the answer to an RFI. The changes it makes should end up on the as-built drawings.

Frequently asked questions

Does an ASI change the contract price?

It is not meant to. An ASI is for minor changes with no change in cost or time. If you think it does cost money, give written notice as your contract requires.

Who issues an ASI?

The architect. It goes to the general contractor, who sends it to the subcontractors it affects.

What should a contractor do when an ASI adds cost?

Tell the architect and owner in writing right away, before doing the work if possible, and follow the change process in the contract.