As-built drawings
As-built drawings are a set of the project drawings marked up by the contractor to show how the work was actually built. They record every place where the finished job differs from the original design.
Last updated
What as-built drawings are
No job is built exactly as drawn. Pipes are rerouted around a beam, a wall moves four inches, a conduit run takes a different path. The contractor marks these changes on a set of drawings, traditionally in red ink, so they are also called redlines. At the end of the job the marked set is handed to the owner.
Some contracts also call for record drawings. That term often means a clean set drafted by the architect from the contractor's as-builts. The two names are sometimes used for the same thing, so check what your contract asks for.
As-builts on a real job
A utility contractor installs a water line along a new road. A buried telephone duct forces the line six feet east of the planned location for a stretch of two hundred feet. The foreman measures the true location from the curb, marks it on the plan sheet that day, and notes the depth. Ten years later a crew digging for a new sign uses those as-builts and misses the water line.
Common mistakes with as-builts
- Waiting until the end of the job and trying to remember where things went.
- Marking changes without dimensions, so the note says moved but not how far.
- Not recording buried or covered work, which is the work nobody can check later.
- Leaving out changes that came from RFIs, ASIs and change orders.
- Keeping the only marked-up set in the job trailer, where it can be lost.
As-builts and Trakend
Trakend does not produce a finished as-built set for you. It helps you keep the notes as you go. Each person can draw on their own markup layer on a sheet with a pen, clouds, arrows and text, and measure distances once the sheet is calibrated. Photos keep the date taken and GPS location, and RFI pins stay on the sheet where the question was asked. See drawing markup and measuring and construction photos.
Related terms
As-builts are part of the closeout package, along with O&M manuals. Many of the changes they show started as an RFI or an ASI.
Frequently asked questions
Who prepares as-built drawings?
The contractor. Each trade usually marks up its own work, and the general contractor collects the sets.
What is the difference between as-built and record drawings?
As-builts are the contractor’s marked-up set. Record drawings are often a clean set prepared from them. Contracts use the words differently, so read yours.
When are as-builts due?
Usually at closeout, and often as a condition of final payment. They are far easier to produce if they are updated every week.
Related
- Drawing markup and measuring: Mark up construction drawings on a phone or tablet, measure distance, area and perimeter to scale, and drop RFI pins. Each person has their own layer.
- Drawing revisions: Upload a new sheet and Trakend files it as the next revision, makes it current for everyone and keeps every older version in the sheet's history.
- Closeout: Closeout is the last phase of a construction project: finishing the punch list, handing over documents and getting final payment. Example and mistakes.
- O&M manual: An O&M (operation and maintenance) manual gives the owner the instructions, schedules and warranties for the building’s equipment. Example and mistakes.
- ASI: An ASI (architect's supplemental instruction) is a written minor change or clarification that does not change price or time. Example and mistakes.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state