RFI (request for information)
An RFI, short for request for information, is a formal written question from the contractor to the design team or the owner. It is used when the drawings, the specifications or the site conditions are unclear, incomplete or in conflict, and the crew needs an answer before it can build.
Last updated
What an RFI is
An RFI asks one clear question and points to the exact sheet, detail or spec section it is about. The architect or engineer answers in writing, and that answer becomes part of the project record. A subcontractor usually sends its RFI to the general contractor, who passes it up to the design team.
An RFI is a question, not a change. If the answer adds cost or time, that is handled afterward with a change order. The RFI is the proof of when the question was asked and what the answer was.
An RFI on a real job
A framing crew finds that the door opening shown on the floor plan is three feet wide, but the door schedule calls for a door that needs a wider opening. The foreman cannot guess. The project manager writes an RFI that names both sheets, attaches a photo of the two drawings side by side, and asks which one is right. Two days later the architect answers that the schedule governs. The crew frames the wider opening and the answer is filed.
Common mistakes with RFIs
- Asking several unrelated questions in one RFI. One question per RFI keeps the answers clear.
- Leaving out the sheet number, detail number or spec section, so the reviewer has to hunt for it.
- Asking by phone or text and never writing it down. Months later nobody can prove what was said.
- Using an RFI to propose a substitution or ask for money. Those have their own paperwork.
- Sending it late. Ask as soon as the problem is found, not the day the crew reaches that area.
How RFIs work in Trakend
In Trakend each project has its own RFI list. RFIs are numbered for you, carry a due date and a priority, and show who has to act next. You can drop a pin on the drawing at the exact spot in question, attach photos, flag a possible cost or schedule impact, and email the RFI as a PDF. Subcontractors on the job can submit RFIs for free. See RFI tracking.
Related terms
An RFI is often confused with a submittal, which asks for approval of a product rather than an answer to a question. All of a job's RFIs together make the RFI log. The person who must act next is said to have the ball in court. An answer that changes cost usually leads to a change order.
Frequently asked questions
Who answers an RFI?
Usually the architect or engineer of record, through the general contractor. On some jobs the owner or the construction manager answers questions about scope or site access.
How long does an RFI answer take?
The contract normally sets the review time. Put a due date on every RFI and follow up before it passes, because an unanswered RFI can hold up the work.
Is an RFI a change order?
No. An RFI only asks a question. If the answer changes the cost or the schedule, the change is priced and approved separately as a change order.
Related
- RFI tracking: Keep one numbered RFI log per project with a reviewer, ball in court, due dates, overdue flags, cost and schedule impact, drawing pins and PDF export.
- RFI vs submittal: RFI vs submittal explained: an RFI asks a question about the documents, a submittal asks for approval of what you plan to install. When to use each.
- Submittal: A submittal is a package the contractor sends for approval before buying or building: shop drawings, product data or samples. Example and mistakes.
- RFI log: An RFI log is the running list of every request for information on a project, with dates, status and who has to answer. Example and common mistakes.
- Ball in court: Ball in court names the person or company that has to act next on an RFI, submittal or other open item. Example, common mistakes, related terms.