Change order tracking from first price to final billing

A change order is only worth something when it is priced, approved and billed. Trakend keeps every change order on a project in a log, applies your markups the same way every time, and puts each approved change on the next pay application so it is not forgotten.

Last updated

Where change orders go missing

Most contractors do not lose money on change orders because the price was wrong. They lose it because the change lived in an email thread. One version was sent to the owner, another was saved on a laptop, and nobody could say which one was approved. Months later the job closes out and a signed change is found that never made it onto a bill.

A second problem sits on the cost side. When a subcontractor's change is approved, the job now owes more money, but the budget still shows the old number until someone updates a spreadsheet.

Two logs on every project

Trakend separates the two directions money moves. One log holds the change orders you send up to the owner or the GC. These change the contract value. The other log holds the change orders your subcontractors send to you. These count as committed cost on their cost code, so the budget shows what the job really owes.

A subcontractor working in your project only ever sees its own change orders. It does not see what you sent the owner or what another sub asked for.

Pricing with rules instead of memory

Status you can read at a glance

Each change order is draft, submitted, in revision, approved, rejected, executed or void. Only people with approval rights can approve. Every change order prints as a PDF with your logo, and the project change order report lists all of them with totals, which is what most owners ask for at the monthly meeting.

When an owner change order is approved or executed, Trakend adds it to the project's draft pay application as its own line. Nobody has to remember to carry it over.

Field tickets feed the change order

Extra work that was done on time and material starts as a signed T&M ticket. One ticket can become a new change order, or a week of tickets can be added to one draft. Used tickets lock.

Who uses it and what it replaces

Project managers write and price change orders. Owners, company admins or others with approval rights approve them. Superintendents feed in tickets and photos from the field. It replaces the change order spreadsheet, the Word template with a markup formula somebody typed years ago, and the email folder called Pending COs.

Frequently asked questions

Can I set different markups for labor and materials?

Yes. Overhead and profit are set separately for labor, materials, equipment and subcontracted work, company-wide or per project.

Do approved change orders show up on the pay application?

Yes. An approved or executed owner change order is added to the draft pay application as its own line.

Can a subcontractor submit a change order to us in Trakend?

Yes. Subcontractors you invite to the project can submit their own change orders free. You review them in the subcontractor log.

Does a change order change the cost budget?

No. An owner change order changes the contract value. A subcontractor change order adds committed cost. The original cost budget stays as you set it.