Addendum

An addendum is a written change or clarification to the bidding documents that is issued before bids are due or before the contract is signed. It becomes part of the contract documents, so the price you give is expected to include it.

Last updated

What an addendum is

During bidding, contractors ask questions and the design team finds things to fix. Instead of reissuing the whole set, the architect sends an addendum. It can change drawings, replace spec sections, answer bidder questions, or move the bid date. Addenda are numbered in order, and most bid forms ask the bidder to list each addendum received.

The plural is addenda. The key point is timing. An addendum changes the documents before there is a contract. After the contract is signed, changes are made with other documents.

An addendum on a real bid

A site work contractor is bidding a parking lot. Four days before the bid, Addendum 2 arrives. It changes the pavement section from four inches of asphalt to five and adds a storm inlet. The estimator who reads it adjusts the quantities. A competitor who misses it bids the thinner section, wins the job, and is now bound to build the thicker one at the lower price, because the addendum is part of the contract.

Common mistakes with addenda

Addenda and Trakend

Trakend is used to run the job after award, and it does not have a bid or addendum module. Once the project starts, addenda matter in two places. Revised sheets are uploaded to the plan set, where a sheet with an existing number is filed as the newer revision. The addendum documents themselves are kept in the project's files so anyone can open them. See drawing revisions.

Related terms

After the contract is signed, a minor design change comes as an ASI, and a change in price or time comes as a change order. Questions during construction are sent as an RFI.

Frequently asked questions

Is an addendum part of the contract?

Yes. Addenda issued before the contract is signed are normally listed in the contract and carry the same weight as the original drawings and specs.

What is the difference between an addendum and a change order?

Timing. An addendum changes the documents before the contract is signed. A change order changes the contract after it is signed.

What is the plural of addendum?

Addenda. You will also hear people say addendums on site, and everyone knows what is meant.