Unit price contract

In a unit price contract the contractor is paid a fixed price for each unit of work, such as per cubic yard, per linear foot or per ton. The final amount is the unit prices multiplied by the quantities actually installed and measured.

Last updated

What a unit price contract is

Unit prices are used when the kind of work is clear but the amount is not. Road work, utilities, earthwork and paving are common examples. The bid form lists items with estimated quantities. The contractor fills in a price for each unit. The low bid is found by multiplying it all out, but payment follows the measured quantities, not the estimates.

That puts quantity risk on the owner and price risk on the contractor. If there is more rock than expected, the owner pays for more units. If the contractor's price per unit was too low, the contractor loses on every unit.

A unit price contract on a real job

A utility contractor bids a sewer job with eight-inch pipe at a set price per foot, manholes at a price each, and rock excavation at a price per cubic yard. The plans estimate 1,200 feet of pipe. The final measured length is 1,260 feet, so the contractor is paid for 1,260. Each month the inspector and the foreman agree on the footage installed, and that count drives the bill.

Common mistakes with unit prices

Unit price work in Trakend

Trakend's pay applications bill each schedule of values line by percent complete or by dollar amount, not by counting units. On unit price work you work out the amount from the measured quantities and enter it. The budget can hold a quantity and a cost per unit on each cost code, daily reports and photos record what was installed each day, and extra work is tracked on T&M tickets. See pay applications and construction budget.

Related terms

The opposite approach is a lump sum contract. Unplanned work may still be paid on a T&M ticket. Quantities are usually tracked by cost code and recorded in the daily report.

Frequently asked questions

Who carries the risk in a unit price contract?

The owner carries the risk that quantities are higher than estimated. The contractor carries the risk that each unit costs more to build than the price given.

How is progress billed on unit price work?

By the quantity of each item completed and accepted in the period, multiplied by its unit price.

Can a contract mix lump sum and unit prices?

Yes. Many contracts have a lump sum for the defined work and unit prices for items such as rock removal or extra pipe.