Cost code
A cost code is a short number or label that sorts every dollar a job spends into a category of work, such as 03-300 for cast-in-place concrete. The estimate, the budget, purchase orders, invoices and labor hours all carry the same codes, so planned cost and actual cost can be compared line by line.
Last updated
What a cost code is
Without cost codes, a contractor knows only whether the whole job made or lost money, and only at the end. With them, the contractor can see in week three that formwork labor is running over while rebar is under.
Many companies base their list on the CSI MasterFormat divisions, where concrete is division 03 and electrical is division 26. Others write their own list around the way they build. A code is often paired with a cost type, such as labor, material, equipment or subcontract. The best list is the shortest one that still answers the questions the company asks about its jobs.
Cost codes on a real job
A concrete subcontractor budgets a slab job with codes for layout, formwork, rebar, place and finish, and curing. Each supplier invoice is coded when it is approved. Each crew's hours go to the code they worked. Halfway through, the place and finish code has used most of its labor budget with a third of the slab still to pour. The project manager sees it while there is still time to change the crew size and pour sequence.
Common mistakes with cost codes
- Having hundreds of codes, so the field picks whichever one is at the top of the list.
- Changing the code list from job to job, which makes it impossible to compare jobs.
- Coding costs at the end of the month from memory instead of when the invoice or time card comes in.
- Estimating with one set of categories and tracking with another.
- Letting uncoded costs pile up in a miscellaneous bucket.
Cost codes in Trakend
In Trakend a company keeps cost code presets in Settings and applies them to a project's budget, merging with or replacing what is there. Each code has a budget, and can carry a quantity and a cost per unit. Purchase order lines, vendor invoice lines, expenses and schedule of values lines are coded to it, and the budget shows committed, actual and remaining for each code, with a separate row for costs that have no code. See cost codes.
Related terms
Costs promised against a code are committed cost. What is left to spend is the cost to complete. Codes feed the WIP report and often line up with the schedule of values.
Frequently asked questions
How many cost codes should a contractor have?
As few as will still tell you where jobs make and lose money. A specialty subcontractor may need twenty to forty. A general contractor usually needs more.
What is the difference between a cost code and a cost type?
The code says what work the cost belongs to. The type says what kind of cost it is: labor, material, equipment, subcontract or other.
Do cost codes have to match the schedule of values?
No. The schedule of values is how you bill the customer. Cost codes are how you track your own cost. They can match, but they do not have to.
Related
- Cost codes: Keep one company cost code list based on CSI divisions, apply it to each project, and use the same codes on budgets, POs, invoices, expenses and billing.
- Budget: Set a job budget by cost code, then watch committed, actual and remaining money update as purchase orders, invoices and expenses are approved.
- Job costing: See budget, committed, spent, projected and remaining cost for every cost code on a job. Actual cost comes from approved invoices, expenses and rentals.
- Committed cost: Committed cost is money a job has promised to spend through purchase orders and subcontracts but has not yet been billed. Example and mistakes.
- Cost to complete: Cost to complete is the estimate of what a job still has to spend to finish. See how it is worked out, an example and the common mistakes.