Daily report (daily log)
A daily report, also called a daily log, is the written record of what happened on a jobsite on one day. It covers the weather, who was on site, the hours worked, the work done, deliveries, visitors, and any delays or problems.
Last updated
What a daily report is
The superintendent or foreman writes it, normally every working day. It is the job's diary. Owners and general contractors often require it by contract, and subcontractors keep their own to protect themselves.
Its real value shows up months later. When there is a question about a delay, an injury, a damaged delivery or how many workers a company had on site, the daily report written that day is the best evidence there is. A report written from memory a week later is worth much less.
A daily report on a real job
A concrete crew loses half a day when a pump truck arrives three hours late and rain starts at one o'clock. The foreman's daily report notes the time the pump arrived, the time the rain started, six workers standing by, and the yards placed before the stop. Four months later the general contractor questions the schedule. The report, with photos from that afternoon, answers it in one page.
Common mistakes with daily reports
- Writing same as yesterday. Every day needs its own facts.
- Leaving out the bad news. Delays and problems are the entries that matter most later.
- Recording a headcount but not hours, or not saying which company the workers belong to.
- Filling out the week's reports on Friday from memory.
- Taking photos but not tying them to the day's report.
Daily reports in Trakend
Trakend's daily report is one screen on a phone, tablet or computer. Weather fills in from the project's zip code, crews and hours add up to man-hours, and photos attach to the day. Finalize Day then gathers the report, that day's safety paperwork and photos into one PDF and emails it to the project's distribution list. See daily reports and Finalize Day.
Related terms
Weather entries in the report support a weather delay record. Extra work noted in a daily report is usually billed on a T&M ticket. The morning safety meeting recorded with it is a toolbox talk.
Frequently asked questions
Who writes the daily report?
The superintendent on a general contractor’s job, or the foreman for a subcontractor’s crew. Whoever runs the work that day should write it that day.
Is a daily report a legal document?
It is a business record, and it is often used as evidence in claims and disputes. That is why it should be factual, dated and written the same day.
How long should daily reports be kept?
With the rest of the project records, for as long as your contract and your company’s record policy require.
Related
- Daily reports: Fill out construction daily reports on a phone: auto weather, crews and man-hours, photos, delays. Finalize the day and email a branded PDF.
- Finalize Day: One tap gathers the daily report, JHAs, toolbox talks and incident reports into a branded PDF and emails it to the project's distribution list.
- How to write a daily report: What goes in a construction daily report, who writes it, and how to do it in a few minutes a day. A plain-English guide with a step-by-step checklist.
- Weather and delay log: Weather fills into each daily report from the project zip code, with morning and afternoon readings, plus a weather-impact flag with hours lost.
- T&M ticket: A T&M ticket records the labor hours, materials and equipment used on extra work, signed in the field the same day. Example and common mistakes.