T&M ticket (time and material ticket)
A T&M ticket, short for time and material ticket, is a daily record of the labor hours, materials and equipment used on extra work. It is signed in the field by someone from the company that will pay for the work.
Last updated
What a T&M ticket is
T&M is used when extra work has to start before anyone can agree on a fixed price, or when the amount of work cannot be known in advance. Instead of a price, the contractor tracks what the work actually takes: who worked and for how many hours, what materials were used, and what equipment ran.
The signature is the heart of it. When the general contractor's superintendent or the owner's representative signs the ticket that day, they are agreeing that those hours and materials were really used. They are not always agreeing to the price. Pricing comes later, at the rates in the contract.
A T&M ticket on a real job
An excavation subcontractor hits buried concrete debris that is not shown on any drawing. The general contractor tells the foreman to remove it on T&M. At the end of the day the foreman writes a ticket: one excavator for five hours, one operator and one laborer for five hours each, and two truckloads hauled off. The superintendent signs it on the foreman's phone before leaving. Three days of tickets later become one change order.
Common mistakes with T&M tickets
- Not getting the ticket signed the same day. A week later nobody remembers the hours.
- Writing a vague description, so the work cannot be told apart from contract work.
- Leaving off equipment, small materials or the foreman's own time.
- Letting signed tickets pile up in a truck instead of sending them to the office.
- Billing the same ticket twice, or never billing it at all.
T&M tickets in Trakend
In Trakend a foreman creates the ticket on site with labor in regular, overtime and double-time hours, plus materials and equipment. The other party signs on the screen, or you upload a photo of a signed paper ticket. Tickets move from draft to submitted, signed, approved and converted. One or several tickets can be turned into a change order, and a used ticket is locked so it can only be billed once. See T&M tickets.
Related terms
Signed tickets are the backup for a change order. On a unit price contract extra work may be paid by measured quantity instead. The day's daily report should mention the same extra work.
Frequently asked questions
What does T&M stand for?
Time and material, sometimes written time and materials. Time is labor and equipment hours. Material is what was used up or installed.
Does a signature on a T&M ticket mean the cost is approved?
Usually it confirms the hours and quantities, not the price or who pays. Check the wording on the ticket and your contract.
Is T&M the same as a change order?
No. The ticket is the daily record of what was used. The change order is the signed agreement that changes the contract amount.
Related
- T&M tickets: Write time and material tickets on a phone, get them signed on screen at the jobsite, and turn signed tickets into change orders that bill only once.
- Change order vs T&M ticket: Change order vs T&M ticket: a change order changes the contract price, a T&M ticket records extra work as it happens. How to use both to get paid.
- Change order: A change order is a signed agreement that changes the contract scope, price or time. See an example, common mistakes and how change orders are tracked.
- Daily report: A construction daily report records each day on site: weather, crews, hours, work done, deliveries and delays. Example, mistakes and related terms.
- Change orders: Price change orders with your own overhead and profit rules, keep owner and sub change orders in separate logs, and bill them on the next pay app.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state