Change order vs T&M ticket
A change order changes the contract. A T&M ticket records the labor, materials and equipment used on extra work while it is happening. You often need both: the ticket is the proof, and the change order is what gets the proof paid.
Last updated
The short answer
| Change order | T&M ticket | |
|---|---|---|
| What it is | A signed change to the contract price, the time, or both | A daily record of labor hours, materials and equipment for extra work |
| When it is written | Before the work when possible, after pricing is agreed | The day the work is done, on site |
| Who signs it | The parties to the contract: owner and contractor, or contractor and sub | The other party's field representative, such as the superintendent |
| What the signature means | The price and the time are agreed | The hours and quantities are agreed. The price usually comes later |
| Where it ends up | Added to the contract sum and billed on the pay application | Attached to a change order as backup |
What a change order is
A change order is a written agreement that changes the contract. It describes the change in scope, the change in price, and any change in time. Once both parties sign it, the contract sum changes, and you can bill the new amount.
The best case is simple. The change is priced, approved and signed before anyone does the work. You know what you will be paid, and the owner knows what it will cost.
What a T&M ticket is
T&M stands for time and materials. A T&M ticket is filled out in the field the day extra work is done. It lists who worked and for how many hours, including overtime, what materials were used, and what equipment was needed. The other party's representative signs it on site.
T&M tickets exist because work does not wait for paperwork. The superintendent says "I need this fixed today, track your time". The crew does it. If the time is not written down and signed that day, it becomes an argument next month about whether three people really spent six hours on it.
- Date, project and a clear description of the extra work and why it was needed
- Who directed the work
- Each worker's name or trade, and regular, overtime and double-time hours
- Materials, with quantities
- Equipment, with hours
- Signature and printed name of the person who approved it, with the date
How they work together
A signed T&M ticket is not payment, and it usually does not change the contract. It is agreement on the facts. To get paid, the tickets are priced using the labor rates and markups in your contract and rolled into a change order. The change order is approved, and then it is billed on the next pay application.
- Extra work is directed in the field.
- The foreman writes a T&M ticket that day and gets it signed.
- The office prices the signed tickets: labor rates, material costs, equipment rates, and overhead and profit.
- The priced tickets become a change order request, with the tickets attached as backup.
- The change order is approved and signed.
- The approved change order goes on the next pay application.
When to use which
- Use a priced change order first when the scope is clear and there is time to price it: added rooms, upgraded finishes, a revised drawing.
- Use T&M tickets when the scope cannot be known ahead of time: hidden conditions, rock, repairs to damage by others, work directed on the spot.
- Use T&M tickets when the two sides cannot agree on a price but the work has to go ahead. Check what your contract says about proceeding with disputed work.
- Use both when in doubt. A ticket costs five minutes. Unbilled work costs the whole job's margin.
Mistakes that lose money
- Doing the work on a handshake and writing it up at the end of the job.
- Tickets with no signature, or signed by someone with no authority.
- Vague descriptions, such as "extra work". Say what, where, and who asked for it.
- Leaving out equipment and small materials.
- Missing the notice deadline. Many contracts require written notice of a change within a set number of days.
- Billing the same ticket twice, or never billing it at all, because tickets are kept in a folder in a truck.
T&M tickets and change orders in Trakend
In Trakend the foreman creates a T&M ticket on a phone, with labor in regular, overtime and double-time hours, plus materials and equipment. The superintendent signs on the screen, or you upload a photo of a signed paper ticket. Tickets move from draft to submitted, signed and approved, so the office always knows which ones can be billed.
A signed ticket converts into a new change order, or several tickets can be added to one draft change order. Your overhead and profit markups are applied by category. Once a ticket is used it is locked, so it can only be billed once. Approved change orders are added to the next pay application automatically. See change orders and pay apps.
Frequently asked questions
Is a signed T&M ticket a change order?
Usually not. A signed ticket confirms the hours, materials and equipment. A change order is what changes the contract price. Check your contract, because some treat a signed ticket as authorization to bill.
Who should sign a T&M ticket?
Someone who represents the party you are working for and who was in a position to see the work, such as the general contractor's superintendent or the owner's representative. Print their name next to the signature.
What if the superintendent will not sign?
Write on the ticket that it was presented and not signed, with the date, time and name, and send a copy by email the same day. A dated written record is far better than nothing.
What does T&M stand for?
Time and materials. The work is paid for based on the actual labor hours, materials and equipment used, plus agreed markups, instead of a fixed price.
Related
- Change orders & pay apps: Change orders with OH&P markup, field-signed T&M tickets, schedule of values, retainage, and G702/G703-style pay application PDFs.
- How G702/G703 pay apps work: How a G702/G703 pay application works: the schedule of values, the continuation sheet columns, retainage, stored materials and the summary math.
- How to write a daily report: What goes in a construction daily report, who writes it, and how to do it in a few minutes a day. A plain-English guide with a step-by-step checklist.
- For subcontractors: Daily reports, JHAs, T&M tickets, change orders, pay apps and crew time clock for specialty contractors. Join your GC's projects free.
- RFI vs submittal: RFI vs submittal explained: an RFI asks a question about the documents, a submittal asks for approval of what you plan to install. When to use each.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state