RFI log

An RFI log is the running list of every request for information on a project. It shows each RFI's number, subject, the date it was sent, who has to answer, the date an answer is due and whether it is still open.

Last updated

What an RFI log is

One RFI is a single question. The log is the view of all of them at once. It lets the project manager see at a glance which questions are waiting on the design team, which are overdue, and which answers may lead to extra cost or lost days.

A good log is reviewed in every owner, architect and contractor meeting. It is also one of the first documents pulled out when there is a claim about a delay, because it shows how long each answer took.

An RFI log on a real job

On a small medical office build, the weekly meeting starts with the RFI log. Twelve RFIs are closed. Three are open. One of the open ones, about the slab depression at a shower, is nine days old and the concrete pour is next week. Because the log shows the date it was sent and the date the pour is planned, the architect agrees to answer by Thursday. Without the log, that question would have stayed buried in email until the trucks were ordered.

Common mistakes with an RFI log

The RFI log in Trakend

In Trakend the RFI list for a project is the log. Each RFI gets the next number automatically, and numbers are never reused, even after a delete. You can filter by status, see an overdue badge when a due date passes, and see who has the ball in court on every line. Each RFI keeps a status timeline, so the dates are recorded as it moves from open to answered to closed. See RFI tracking.

Related terms

The log is made of individual RFIs. Its twin on the approval side is the submittal log. The column that says who must act next is the ball in court.

Frequently asked questions

What columns should an RFI log have?

Number, subject, drawing or spec reference, who asked, who must answer, date sent, date due, date answered, status, and a note on any cost or schedule impact.

Who keeps the RFI log?

Usually the general contractor’s project manager or project engineer. Subcontractors often keep their own short log of the questions they have sent.

How often should the log be reviewed?

At least once a week, normally in the regular project meeting, and any time an open question is about to hold up work.