RFI log
An RFI log is the running list of every request for information on a project. It shows each RFI's number, subject, the date it was sent, who has to answer, the date an answer is due and whether it is still open.
Last updated
What an RFI log is
One RFI is a single question. The log is the view of all of them at once. It lets the project manager see at a glance which questions are waiting on the design team, which are overdue, and which answers may lead to extra cost or lost days.
A good log is reviewed in every owner, architect and contractor meeting. It is also one of the first documents pulled out when there is a claim about a delay, because it shows how long each answer took.
An RFI log on a real job
On a small medical office build, the weekly meeting starts with the RFI log. Twelve RFIs are closed. Three are open. One of the open ones, about the slab depression at a shower, is nine days old and the concrete pour is next week. Because the log shows the date it was sent and the date the pour is planned, the architect agrees to answer by Thursday. Without the log, that question would have stayed buried in email until the trucks were ordered.
Common mistakes with an RFI log
- Keeping the log in a spreadsheet that only one person updates, so it is always a week behind.
- Reusing or skipping numbers, which makes it hard to prove that nothing is missing.
- Not recording the date each answer came back, so response times cannot be shown later.
- Closing an RFI in the log without filing the written answer with it.
- Leaving out RFIs that came from subcontractors. Their questions hold up work too.
The RFI log in Trakend
In Trakend the RFI list for a project is the log. Each RFI gets the next number automatically, and numbers are never reused, even after a delete. You can filter by status, see an overdue badge when a due date passes, and see who has the ball in court on every line. Each RFI keeps a status timeline, so the dates are recorded as it moves from open to answered to closed. See RFI tracking.
Related terms
The log is made of individual RFIs. Its twin on the approval side is the submittal log. The column that says who must act next is the ball in court.
Frequently asked questions
What columns should an RFI log have?
Number, subject, drawing or spec reference, who asked, who must answer, date sent, date due, date answered, status, and a note on any cost or schedule impact.
Who keeps the RFI log?
Usually the general contractor’s project manager or project engineer. Subcontractors often keep their own short log of the questions they have sent.
How often should the log be reviewed?
At least once a week, normally in the regular project meeting, and any time an open question is about to hold up work.
Related
- RFI tracking: Keep one numbered RFI log per project with a reviewer, ball in court, due dates, overdue flags, cost and schedule impact, drawing pins and PDF export.
- RFI (request for information): An RFI (request for information) is a written question about the drawings or specs. See an example, common mistakes and how RFIs are tracked.
- Submittal log: A submittal log, or submittal register, lists every required submittal with its spec section, dates and status. Example, mistakes and related terms.
- Ball in court: Ball in court names the person or company that has to act next on an RFI, submittal or other open item. Example, common mistakes, related terms.
- RFI vs submittal: RFI vs submittal explained: an RFI asks a question about the documents, a submittal asks for approval of what you plan to install. When to use each.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state
