Submittal
A submittal is a package of information the contractor sends to the design team for review before material is ordered or work is built. It shows exactly what the contractor plans to use, so the architect or engineer can confirm it matches the design.
Last updated
What a submittal is
The specifications list which submittals are required. The usual kinds are shop drawings, product data sheets, samples, mock-ups, test reports and certificates. The subcontractor or supplier prepares the package, the general contractor checks it, and the design team returns it with a review stamp.
Common results are approved, approved as noted, revise and resubmit, or rejected. Material should not be ordered or installed until the submittal comes back with an approval.
A submittal on a real job
A mechanical subcontractor has to submit the rooftop units before ordering them. The package has the manufacturer's data sheets with the exact models marked, the electrical data and the curb details. The engineer returns it approved as noted, with one note to change a filter size. The units have a twelve-week lead time, so the day the stamp comes back is the day the order must go in.
Common mistakes with submittals
- Sending the manufacturer's whole catalog without marking which model, size and options apply.
- Submitting too late for the lead time, so the material cannot arrive when the schedule needs it.
- Ordering before the approval comes back, then owning the cost if it is rejected.
- Treating the approval as permission to change the contract. A review stamp does not approve extra cost.
- Ignoring the notes on an approved as noted stamp.
How submittals work in Trakend
Trakend has a submittal register on every project. Each submittal has a type, spec section, reviewer, due date and status, plus a revision number for resubmittals. Enter the date the material is needed on site and its lead time, and Trakend works out the order-by date. One click builds a package with a cover page and every attached PDF merged behind it. See submittal tracking.
Related terms
A submittal asks for approval, while an RFI asks a question. The full list for a job is the submittal log. A cover sheet that lists what was sent is a transmittal. Manuals collected near the end of the job are O&M manuals.
Frequently asked questions
Who approves submittals?
The architect or engineer responsible for that part of the design. The general contractor reviews the package first and then sends it on.
Is a shop drawing a submittal?
Yes. Shop drawings are one kind of submittal. Product data, samples, mock-ups, test reports and certificates are others.
What does approved as noted mean?
The reviewer accepts the submittal as long as the written notes are followed. You can usually proceed without resubmitting, but the notes are part of the approval.
Related
- Submittal tracking: Run the submittal register in one place: bulk setup from spec sections, review status, revisions, order-by dates from lead times and PDF packages.
- RFI vs submittal: RFI vs submittal explained: an RFI asks a question about the documents, a submittal asks for approval of what you plan to install. When to use each.
- Submittal log: A submittal log, or submittal register, lists every required submittal with its spec section, dates and status. Example, mistakes and related terms.
- RFI (request for information): An RFI (request for information) is a written question about the drawings or specs. See an example, common mistakes and how RFIs are tracked.
- Transmittal: A transmittal is a cover sheet that records what documents were sent, to whom, when and why. See an example, common mistakes and related terms.