Home › Guides › RFI vs submittal
RFI vs submittal: what is the difference?
An RFI asks a question. A submittal asks for approval. Both go from the contractor to the design team, both have due dates, and both can hold up a job, which is why they get mixed up. This guide explains each one and when to use it.
Last updated
The short answer
| RFI | Submittal | |
|---|---|---|
| What it is | Request for information: a written question | A package showing what you plan to furnish and install |
| Why you send it | The drawings or specs are unclear, conflict, or are missing something | The contract requires the design team to review products and shop drawings before you order or build |
| What comes back | An answer or a clarification | A review action: approved, approved as noted, revise and resubmit, or rejected |
| When it happens | Any time a question comes up, often during the work | Early, before materials are ordered or fabricated |
| Who starts it | Anyone who finds the problem: a foreman, a sub, the PM | The contractor or sub who supplies the item, following the spec's submittal list |
What an RFI is
RFI stands for request for information. You send one when the contract documents do not tell you what you need to know: a dimension is missing, two drawings disagree, the spec calls for a product that is no longer made, or the field conditions do not match the plans.
A good RFI is short and specific. It names the drawing and detail, describes the problem in one or two sentences, includes a photo or a marked-up sheet, and suggests a solution. A suggested answer gets a faster response, because the reviewer only has to say yes.
- Reference the exact sheet, detail, gridline or spec section.
- Ask one question per RFI.
- Attach a photo or a marked-up drawing.
- Propose a solution when you have one.
- Say when you need the answer and what it is holding up.
- Flag it if the answer may change cost or time.
What a submittal is
A submittal is information the contractor sends to the architect or engineer to show what will actually be installed. The specifications list which submittals are required for each section of work.
The reviewer checks that the product or shop drawing matches the design intent and returns it with an action. Materials should not be ordered or fabricated until the submittal comes back approved, which is why submittals are tied so closely to the schedule.
- Shop drawings: fabrication drawings for steel, rebar, millwork, curtain wall, ductwork.
- Product data: manufacturer cut sheets for fixtures, equipment and materials.
- Samples: physical pieces for color and finish.
- Mock-ups: a built sample of an assembly.
- Test reports, certificates and design calculations.
Why the difference matters
Using the wrong one causes real problems. If you ask a design question inside a submittal, it may be missed, because the reviewer is checking the product and not looking for questions. If you try to get a product substitution approved through an RFI, it may be rejected, because most contracts have a separate process for substitutions.
A submittal also does not change the contract. If an approved shop drawing shows something different from the contract documents, that usually does not relieve the contractor of meeting the contract unless the change was clearly pointed out and accepted. An RFI answer that adds work is not a change order either. If an answer changes cost or time, say so in writing and follow your contract's change process.
Tracking both without losing track
Both need a log. For RFIs, track the number, subject, date sent, who has to respond, the due date and the status. An unanswered RFI is a delay you want on record.
For submittals, the key date is not when it is due back. It is when the material has to be ordered. Work backward: the date it is needed on site, minus the lead time, minus the review time. That gives you the date the submittal must go out.
- Build the submittal register from the specs at the start of the job.
- Rank it by lead time. Long-lead items go first.
- Check both logs every week and chase the overdue items.
- Keep who has the next move, often called ball-in-court, on every item.
RFIs and submittals in Trakend
Trakend keeps an RFI log and a submittal register in each project. Both are numbered automatically and both track the reviewer, the ball-in-court, the due date and the status. You can pin an RFI to the exact spot on a drawing, and flag cost and schedule impact.
For submittals, enter the needed-on-site date and the lead time, and Trakend works out the order-by date and flags the late ones. A package button builds a cover page and merges the attached PDFs into one file. Subcontractors on your project can send RFIs and submittals at no cost. See RFI and submittal tracking.
Frequently asked questions
Is an RFI a change order?
No. An RFI is a question, and the response is an answer. If the answer adds cost or time, that has to go through the contract's change order process.
Can a subcontractor send an RFI?
Yes. Subcontractors usually send RFIs to the general contractor, who reviews them and passes them to the architect or engineer if needed.
What does "approved as noted" mean on a submittal?
The reviewer accepts the submittal with the corrections marked on it. In most cases you can proceed if you follow the notes, but check what your contract says.
How long does the architect have to respond?
The contract documents set the review time for RFIs and submittals. Check your contract, and build that time into your schedule.
Related
- RFIs & submittals: Track RFIs and submittals with auto-numbering, ball-in-court, due dates, lead-time order-by dates, drawing pins and combined PDF packages.
- Plans & drawings: Upload a drawing set once. Trakend splits it into sheets, reads sheet numbers, tracks revisions, and lets your team mark up and measure.
- Change order vs T&M ticket: Change order vs T&M ticket: a change order changes the contract price, a T&M ticket records extra work as it happens. How to use both to get paid.
- For general contractors: Run every job from one app: field reports, safety, drawings, RFIs, submittals, schedule, change orders and pay apps. Subs join free.
- Scheduling: Drag-and-drop Gantt schedules with milestones, linked tasks and baselines, a weekly crew planner, and calendar feeds for Outlook and Google.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state
