Submittal log (submittal register)

A submittal log, also called a submittal register, is the list of every submittal the contract requires. For each one it shows the spec section, who is responsible, when it must be sent, when it came back and what the reviewer decided.

Last updated

What a submittal log is

The log is built at the start of the job by reading the specifications section by section and listing each required item. From then on it is a planning tool. Working back from the date material is needed on site, it tells you when each submittal has to go out so there is time for review, a possible resubmittal, and the supplier's lead time.

The log also shows the whole team where the hold-ups are: with the subcontractor who has not sent the package, or with the reviewer who has not returned it.

A submittal log on a real job

A general contractor on a school addition lists sixty submittals in the first two weeks. Door hardware has a long lead time, so its row shows an order-by date only five weeks after the start. The hardware supplier has not sent the package. The project engineer sees the row turn late in the log and calls the supplier that day, instead of finding out in month four that the doors cannot be locked.

Common mistakes with a submittal log

The submittal log in Trakend

In Trakend the register is a table of every submittal by number, title, spec section, needed-on-site date, status and ball in court, and it exports to CSV. To set it up quickly you can paste a list of spec sections or upload a CSV and create up to 200 draft submittals at once. Items that are late, or due within seven days of their order-by date, are flagged. See submittal tracking.

Related terms

Each row in the log is one submittal. The matching list for questions is the RFI log. Who must act next on each row is the ball in court. Many of the last rows feed the closeout package.

Frequently asked questions

What is the difference between a submittal log and a submittal register?

They are two names for the same list. Some contracts use one word and some use the other.

When should the submittal log be created?

Right after the contract is signed, before the first submittals are due. Many owners ask to see it within the first few weeks.

What should a submittal log track?

Number, title, spec section, responsible subcontractor, type, date required on site, lead time, date sent, date returned, result, and revision number.