Schedule of values (SOV)

A schedule of values, or SOV, is a list that breaks the total contract price into line items, each with a dollar value. The lines add up to exactly the contract amount, and every monthly bill is measured against them.

Last updated

What a schedule of values is

On most commercial jobs the contractor is paid monthly for the work done so far. The SOV is the yardstick. Each line is a piece of the work, such as mobilization, underground plumbing, rough-in or fixtures. Each month the contractor says how far along each line is, and the bill is the value of that progress.

The owner or general contractor usually has to approve the SOV before the first bill. Reviewers look for lines that are clear enough to check on a site walk and that do not put too much of the money at the front of the job.

A schedule of values on a real job

A painting subcontractor has a contract for ninety thousand dollars. Its SOV has nine lines: mobilization, surface prep by floor, primer, finish coats by floor, and touch-up. In the second month, prep on floors one and two is done and primer on floor one is half done. The bill is simply those lines at those values. The general contractor's project manager can walk the floors and agree in ten minutes.

Common mistakes with a schedule of values

The schedule of values in Trakend

In Trakend each project has a schedule of values with categories, cost codes and a retainage rate on each line. You can type it in or generate the lines from your cost-code budget, one per code or one per division. An approved SOV is required before the first pay application, and subcontractors submit theirs to the general contractor for approval the same way. See schedule of values.

Related terms

The SOV is the base of every pay application. Money held back from each line is retainage. It is most common on a lump sum contract. Internal tracking uses cost codes, which may or may not match the SOV lines.

Frequently asked questions

Who prepares the schedule of values?

The contractor being paid. A subcontractor prepares one for the general contractor, and the general contractor prepares one for the owner.

How detailed should an SOV be?

Detailed enough that someone can walk the job and agree on each line’s progress, but not so detailed that billing takes all day. Many subcontractors use ten to thirty lines.

Can the schedule of values change?

The original lines should stay fixed once approved. Approved change orders are added as new lines.

This page is general information, not legal, tax or insurance advice. Your contract and your state’s laws decide what applies on your job.