Retainage (retention)
Retainage, also called retention, is a part of each progress payment that the owner or general contractor holds back until the job, or a stage of it, is complete. It is money the contractor has earned but has not yet been paid.
Last updated
What retainage is
The idea is to give the paying party some security that the work will be finished and the punch list completed. The contract sets the rate, which is commonly five or ten percent of each bill. The amount held grows month by month and is released near the end, often at substantial completion or final completion.
Retainage flows down. If the owner holds it from the general contractor, the general contractor normally holds it from the subcontractors. Many states have laws that limit the rate or set deadlines for paying it, especially on public work, so the rules depend on where the job is.
Retainage on a real job
A drywall subcontractor bills fifty thousand dollars in March on a job with ten percent retainage. The check is for forty-five thousand. Five thousand is held. By the end of a four hundred thousand dollar contract, forty thousand is being held. That may be most of the profit on the job, and it is paid only after the punch list is done and the closeout paperwork is turned in.
Common mistakes with retainage
- Forgetting to bill for retainage at the end of the job. It is not paid automatically.
- Not tracking retainage held as money owed to you, so cash flow looks better than it is.
- Missing a contract clause that reduces the rate partway through the job.
- Finishing the work but not the closeout documents that release the money.
- Holding retainage from subcontractors at a different rate than the contract allows.
Retainage in Trakend
In Trakend each project has a default retainage rate, which is 10% unless you change it, and the rate can be overridden on single lines of the schedule of values. Each pay application shows the retainage held, and retainage can be released in any period. Retainage held on vendor invoices is tracked too. See retainage tracking.
Related terms
Retainage is calculated on each pay application from the schedule of values. It is usually released around substantial completion and closeout, often in exchange for a final lien waiver.
Frequently asked questions
Is retainage the same as retention?
Yes. They are two words for the same held-back money.
When is retainage paid?
When the contract says. Common trigger points are substantial completion, completion of the punch list, or final acceptance. State law can also set deadlines.
Can retainage be reduced during the job?
Some contracts and some state laws reduce or stop retainage after the job reaches a certain point. Read the payment section of your contract.
This page is general information, not legal, tax or insurance advice. Your contract and your state’s laws decide what applies on your job.
Related
- Retainage tracking: Track retainage held on every pay application line, override the rate where the contract says so, release it in any period, and see what subs are owed.
- Pay application: A pay application is the contractor’s periodic request for payment, based on work completed against the schedule of values. Example and mistakes.
- Schedule of values: A schedule of values breaks the contract price into line items that add up to the total and is used to bill each month. Example and common mistakes.
- Substantial completion: Substantial completion is the point when a project is finished enough for the owner to use it as intended. Example, common mistakes, related terms.
- Lien waiver: A lien waiver is a signed document giving up the right to file a lien for a payment. Learn the four common types, an example and common mistakes.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state