How G702 and G703 pay applications work
On most commercial jobs you do not send an invoice. You send a pay application: a summary page and a line-by-line sheet showing how much of each part of the contract is complete. The most common format follows the AIA G702 and G703 forms. This guide explains how it works, line by line.
Last updated
The two forms
G702 is the Application and Certificate for Payment. It is the one-page summary: the contract amount, change orders, what has been completed, retainage, what has already been paid, and what is due now. It has a place for the contractor to sign and for the architect to certify the amount.
G703 is the Continuation Sheet. It lists every line of the schedule of values and shows how much of each line is complete. The totals at the bottom of the G703 feed the summary on the G702.
G702 and G703 are AIA Contract Documents, published by the American Institute of Architects. Many owners require the official forms, and others accept the same layout. Check your contract.
It starts with the schedule of values
The schedule of values, or SOV, breaks the contract sum into lines: mobilization, each phase or area of work, major materials, closeout. The total of the lines equals the contract sum. The owner or general contractor approves the SOV before the first pay application, and you bill against the same lines every month.
A good SOV has enough lines that percent complete is easy to agree on, but not so many that the pay app takes a day to fill out. Lines that match how the job is built, by building, floor, area or system, are easier to defend.
The continuation sheet (G703), column by column
| Column | What goes in it |
|---|---|
| A. Item number | The line number from the schedule of values |
| B. Description of work | What the line covers |
| C. Scheduled value | The dollar amount assigned to the line |
| D. Work completed, from previous application | Everything billed for this line on earlier pay apps |
| E. Work completed, this period | The value of work done since the last pay app |
| F. Materials presently stored | Materials delivered and stored but not yet installed, and not already in D or E |
| G. Total completed and stored to date | D plus E plus F, and the percentage of the scheduled value that represents |
| H. Balance to finish | Scheduled value minus total completed and stored |
| I. Retainage | The amount held back on this line |
The summary (G702), line by line
- Original contract sum.
- Net change by change orders: approved additions minus approved deductions.
- Contract sum to date: line 1 plus line 2.
- Total completed and stored to date: the total of column G on the continuation sheet.
- Retainage: a percentage of completed work plus a percentage of stored material.
- Total earned less retainage: line 4 minus line 5.
- Less previous certificates for payment: what was certified on earlier pay apps.
- Current payment due: line 6 minus line 7.
- Balance to finish, including retainage: line 3 minus line 6.
Retainage
Retainage is money the owner holds back from each payment until the work is finished, as security that the job will be completed. The percentage is set by the contract, and state law limits it on some kinds of projects. Some contracts reduce it partway through the job, and it is released at or near the end.
On the pay app, retainage is calculated on the work completed and usually on stored materials too. It lowers the current payment due, and it adds up in the balance to finish, including retainage, at the bottom of the summary.
Stored materials
If your contract allows it, you can bill for materials that have been delivered and properly stored but not yet installed. They go in column F. Owners often ask for proof, such as invoices, photos, and insurance for materials stored off site. Once the material is installed, its value moves from the stored column into work completed on a later pay app, so it is never billed twice.
Change orders on a pay application
Only approved change orders belong on a pay app. They are usually added as their own lines at the bottom of the continuation sheet, and they change the contract sum to date on the summary. Billing for pending changes is one of the most common reasons a pay app is sent back.
Common reasons a pay app gets rejected
- The math does not carry forward from last month's application.
- Percent complete is higher than what the field shows.
- Unapproved change orders are included.
- Stored materials are billed with no backup.
- Lien waivers, certified payroll or other required attachments are missing.
- It was submitted after the billing deadline in the contract.
Pay applications in Trakend
Trakend builds G702/G703-style pay applications from your approved schedule of values. You bill each line by percent complete or by dollar amount, including stored materials, and the previous application rolls forward automatically. Approved change orders are added to the draft as their own lines. Retainage defaults per project, can be changed by line, and can be released in any period.
The result is a PDF with an architect's certificate block and an optional notary block. Subcontractors on your project can submit their own SOV and pay applications to you at no cost. See change orders and pay apps.
Frequently asked questions
What is the difference between G702 and G703?
G702 is the summary page with the contract totals, retainage and amount due, and the signature and certification blocks. G703 is the continuation sheet that lists each schedule of values line and how much of it is complete.
Do I have to use the official AIA forms?
Only if your contract requires them. The official forms come from the American Institute of Architects. Many owners and general contractors accept a pay application in the same format.
How often do you submit a pay application?
Usually once a month, on the date set in the contract. Missing the billing date often pushes payment to the next cycle.
Can subcontractors use the G702/G703 format?
Yes. General contractors often require their subcontractors to bill in the same format, so the sub's numbers roll up into the pay application to the owner.
Related
- Change orders & pay apps: Change orders with OH&P markup, field-signed T&M tickets, schedule of values, retainage, and G702/G703-style pay application PDFs.
- Change order vs T&M ticket: Change order vs T&M ticket: a change order changes the contract price, a T&M ticket records extra work as it happens. How to use both to get paid.
- For subcontractors: Daily reports, JHAs, T&M tickets, change orders, pay apps and crew time clock for specialty contractors. Join your GC's projects free.
- For general contractors: Run every job from one app: field reports, safety, drawings, RFIs, submittals, schedule, change orders and pay apps. Subs join free.
- Pricing: Flat monthly plans from $299 to $2,499 (unlimited users). Every feature, unlimited storage (fair use), free subs, no setup fee, 30-day trial.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state