Punch list
A punch list is the list of items that still have to be fixed or finished near the end of a construction job before the owner accepts it as complete. Typical items are small: a scratched door, a missing cover plate, paint touch-up, a sticking window.
Last updated
What a punch list is
The list is usually made on a walk-through of the building by the owner, the architect and the general contractor around the time of substantial completion. Each item says what is wrong, where it is, and which trade has to fix it. The general contractor hands the items to its subcontractors, checks the fixes, and the owner or architect confirms the list is done.
Money rides on it. Final payment and retainage are normally held until the punch list is complete. Many contractors run their own internal list first, before the owner's walk, so that the official list is short.
A punch list on a real job
On a dental office build-out, the walk-through produces forty-two items. Item 17 reads: operatory 3, base cabinet door rubs on the frame, millwork subcontractor. The superintendent sends each trade its items with a photo and a due date. Over the next week the trades mark their items resolved, the superintendent checks each one in person, and the architect signs off on the last three on the second walk.
Common mistakes with punch lists
- Vague items such as fix paint in hallway, with no location or photo.
- No single owner for an item, so two trades each assume the other will do it.
- Adding new items to the list for weeks. Agree on one list and one walk.
- Marking items done without anyone verifying them.
- Letting the punch list become a place for unfinished contract work that should have been done months ago.
Punch lists in Trakend
Trakend's punch list is organized by phase, such as a floor or the final walk-through. Each item has a title, description, priority, assignee, due date, photos and comments, and can be pinned to the exact spot on a drawing. Items move from open to in progress to resolved to verified, and verified records who checked it and when. Assignees and watchers are notified as items move. It does not export to PDF today. See punch list.
Related terms
The punch list is created around substantial completion and has to be cleared as part of closeout. Finishing it usually releases retainage. A later list made near the end of the warranty is a warranty walk.
Frequently asked questions
Who creates the punch list?
Usually the owner and architect with the general contractor, on a walk-through. The general contractor then assigns the items to subcontractors.
When is the punch list made?
Around substantial completion, when the space can be used but small items remain.
Why is it called a punch list?
The common explanation is that items on a paper list were once punched with a hole as they were completed.
Related
- Punch list: Track punch items by phase with photos, a pin on the drawing, an assignee and a due date. Items move from Open to Verified, with alerts at each step.
- Substantial completion: Substantial completion is the point when a project is finished enough for the owner to use it as intended. Example, common mistakes, related terms.
- Closeout: Closeout is the last phase of a construction project: finishing the punch list, handing over documents and getting final payment. Example and mistakes.
- Retainage: Retainage is a share of each progress payment held back until the work is finished. See an example, common mistakes and how retainage is tracked.
- Warranty walk: A warranty walk is an inspection held before the warranty period ends, to list defects the contractor must fix. Example, mistakes, related terms.