Look-ahead schedule
A look-ahead schedule is a short-term plan that shows, in detail, the work planned for the next few weeks. Two-week and three-week look-aheads are the most common, and some jobs use six.
Last updated
What a look-ahead schedule is
The master schedule covers the whole job in broad activities, often months long. Nobody can run a crew from that. The look-ahead takes the next slice of the master schedule and breaks it into days: which crew is in which area, what is being delivered, which inspections are needed and what has to be finished first.
The superintendent usually writes it each week and reviews it with the foremen and subcontractors in the coordination meeting. Its real job is to expose problems early. If the look-ahead shows the electrician and the drywall crew in the same corridor on Wednesday, that gets solved on Friday in the trailer instead of Wednesday in the corridor.
A look-ahead on a real job
On a two-story office shell, the superintendent's three-week look-ahead shows the slab on deck pour on Tuesday of week one, which means the deck inspection must happen Monday and the pump must be booked now. Stud framing on level one starts the following Monday. The framer says the studs are not on site yet. Because that came up two weeks ahead, the delivery is moved up and no days are lost.
Common mistakes with look-aheads
- Copying last week's look-ahead and shifting the dates without checking what was really done.
- Writing it alone in the trailer without the foremen and subcontractors who have to carry it out.
- Leaving out deliveries, inspections and submittal approvals, which are what usually stop work.
- Letting it drift away from the master schedule until the two tell different stories.
- Making it so detailed that nobody reads it.
Look-aheads in Trakend
Trakend's weekly planner is a look-ahead at crew level. Each subcontractor or crew has a row with the days of the week, a week can be copied forward, and from Thursday on the planner opens to next week. Subcontractors can edit their own rows. The planned crews pre-fill that day's daily report, and the planner exports to PDF for the coordination meeting. The longer view is the Gantt schedule. See weekly crew planner.
Related terms
The look-ahead is drawn from the master schedule, whose longest chain of activities is the critical path. What actually happened each day is recorded in the daily report. Late answers that threaten the look-ahead show up in the RFI log.
Frequently asked questions
How far ahead should a look-ahead go?
Two or three weeks is typical. Jobs with long-lead deliveries or tight phasing may use six.
Who prepares it?
Usually the superintendent, with input from each foreman and subcontractor.
How is it different from the master schedule?
The master schedule covers the whole job at a high level. The look-ahead covers the next few weeks in day-by-day detail.
Related
- Weekly crew planner: Plan next week by crew and by sub, Monday to Sunday. Copy a week forward, share rows with the right people, and pre-fill each day's daily report.
- Gantt chart schedule: Build the project schedule as a Gantt chart: drag bars, link tasks with lag days, set milestones, save a baseline and export a PDF for the meeting.
- Scheduling: Drag-and-drop Gantt schedules with milestones, linked tasks and baselines, a weekly crew planner, and calendar feeds for Outlook and Google.
- Critical path: The critical path is the longest chain of linked activities in a schedule. A delay to any of them delays the finish date. Example and mistakes.
- Daily report: A construction daily report records each day on site: weather, crews, hours, work done, deliveries and delays. Example, mistakes and related terms.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state