Look-ahead schedule

A look-ahead schedule is a short-term plan that shows, in detail, the work planned for the next few weeks. Two-week and three-week look-aheads are the most common, and some jobs use six.

Last updated

What a look-ahead schedule is

The master schedule covers the whole job in broad activities, often months long. Nobody can run a crew from that. The look-ahead takes the next slice of the master schedule and breaks it into days: which crew is in which area, what is being delivered, which inspections are needed and what has to be finished first.

The superintendent usually writes it each week and reviews it with the foremen and subcontractors in the coordination meeting. Its real job is to expose problems early. If the look-ahead shows the electrician and the drywall crew in the same corridor on Wednesday, that gets solved on Friday in the trailer instead of Wednesday in the corridor.

A look-ahead on a real job

On a two-story office shell, the superintendent's three-week look-ahead shows the slab on deck pour on Tuesday of week one, which means the deck inspection must happen Monday and the pump must be booked now. Stud framing on level one starts the following Monday. The framer says the studs are not on site yet. Because that came up two weeks ahead, the delivery is moved up and no days are lost.

Common mistakes with look-aheads

Look-aheads in Trakend

Trakend's weekly planner is a look-ahead at crew level. Each subcontractor or crew has a row with the days of the week, a week can be copied forward, and from Thursday on the planner opens to next week. Subcontractors can edit their own rows. The planned crews pre-fill that day's daily report, and the planner exports to PDF for the coordination meeting. The longer view is the Gantt schedule. See weekly crew planner.

Related terms

The look-ahead is drawn from the master schedule, whose longest chain of activities is the critical path. What actually happened each day is recorded in the daily report. Late answers that threaten the look-ahead show up in the RFI log.

Frequently asked questions

How far ahead should a look-ahead go?

Two or three weeks is typical. Jobs with long-lead deliveries or tight phasing may use six.

Who prepares it?

Usually the superintendent, with input from each foreman and subcontractor.

How is it different from the master schedule?

The master schedule covers the whole job at a high level. The look-ahead covers the next few weeks in day-by-day detail.