The master schedule says the slab is poured in March. The weekly plan says who shows up Tuesday. Trakend's weekly planner is the second one: a simple grid with a row for each crew or subcontractor and a column for each day, built for the Friday planning meeting and for the superintendent who has to make the week work.
Last updated
The whiteboard problem
Ask most superintendents where next week's plan is and they will point to a whiteboard in the trailer, or a sheet they collect from each sub on Friday. It works until someone needs it who is not standing in the trailer. The PM calls to ask who is on site Wednesday. A sub's office does not know their crew was moved to Thursday. On Monday the board is wiped and the record of what was planned is gone.
A long-range schedule cannot fix this, because it is too coarse. The weekly plan needs its own tool.
One row per crew, one column per day
- Each crew or subcontractor gets a row, with Monday through Sunday across the top.
- Pick the sub or crew from your list, or type any name, then write a short description of their work for each day.
- Copy a whole week forward when next week looks like this week, then change only what is different.
- From Thursday on, the planner opens to next week by default, because that is the week you are planning.
- Export the week to PDF to hand out or pin up in the trailer.
Decide who sees each entry
Every entry has a visibility setting. It can be private to you, shared with named people, or visible to everyone on the project. A superintendent can sketch a draft plan privately and open it up after the planning meeting.
Subcontractors on the project see what has been shared with them and can edit only their own rows. That turns the Friday paper sheet into something each sub fills in for themselves, and you see all of it side by side.
The plan becomes the start of the daily report
This is where the planner saves real time. When a new daily report is started, the crews planned for that day are already filled in. The superintendent adjusts what changed: a crew that came short, a sub that did not show. Nothing that has already been typed on the report is overwritten.
Over a few weeks you also get something a whiteboard never gives you, which is a record of what was planned next to what actually happened.
How it sits beside the schedule and tasks
The Gantt schedule holds phases, milestones and the links between them. The weekly planner holds the crew-level detail for the next seven days. They answer different questions, and most teams use both. Some call the weekly plan a look-ahead schedule.
The planner also appears on the company Tasks page, so a manager can see the week across jobs without opening each project.
Who uses it and what it replaces
Superintendents and foremen build the plan. Subcontractor foremen fill in their own rows from their free accounts. Project managers and the office read it to know who is where. It replaces the trailer whiteboard, the weekly planning sheet collected by hand, and the Sunday night group text. The planner works in the web app on any phone, tablet or computer and is included on every plan, with no charge for the subs who use it.
Frequently asked questions
Is the weekly planner the same as the project schedule?
No. The schedule is the whole-job Gantt chart. The weekly planner is the day-by-day plan for each crew or sub for one week.
Can subcontractors enter their own plan?
Yes. Subs on the project can edit their own rows and see the entries that have been shared with them. They do not pay for an account.
Does the weekly plan fill in the daily report?
Yes. A new daily report starts with the crews planned for that day. Anything already typed on the report is left alone.
Can I print the weekly plan?
Yes. The planner exports the week to a PDF.
Related
- Scheduling: Drag-and-drop Gantt schedules with milestones, linked tasks and baselines, a weekly crew planner, and calendar feeds for Outlook and Google.
- Gantt chart schedule: Build the project schedule as a Gantt chart: drag bars, link tasks with lag days, set milestones, save a baseline and export a PDF for the meeting.
- Daily reports: Fill out construction daily reports on a phone: auto weather, crews and man-hours, photos, delays. Finalize the day and email a branded PDF.
- Tasks: A task board for each project and one list across all jobs: assignee, priority, due date, comments, attachments and a PDF for the next meeting.
- Look-ahead schedule: A look-ahead schedule is a short-term plan of the next two to six weeks of work, by day and by crew. Example, common mistakes and related terms.
- Subcontractor portal: Invite subcontractors to your projects at no cost. They file JHAs, RFIs, submittals, change orders and pay apps, and see only their own paperwork.