Home › Glossary › Critical path

Critical path

The critical path is the longest chain of dependent activities in a project schedule. It sets the earliest date the job can finish. If any activity on it slips by a day, the finish date slips by a day unless time is made up somewhere else on the path.

Last updated

What the critical path is

A schedule is a network of activities tied together by logic: the slab cannot be poured until the rebar is inspected, and the walls cannot be framed until the slab is poured. Critical path method scheduling, usually shortened to CPM, works out the longest route through that network.

Activities that are not on the critical path have float, which is the number of days they can be late without moving the finish date. Critical activities have none. The path can change during the job. When a non-critical activity uses up its float, it becomes critical. That is why the schedule has to be updated with real progress to stay useful.

The critical path on a real job

A small warehouse has two chains of work after the slab. One is steel erection, roofing and overhead doors, which takes forty working days. The other is underground site utilities and paving, which takes twenty-five. Both must be done to finish. The steel chain is the critical path, and the site work has fifteen days of float. A week of rain that stops paving does not move the finish date. A one-week delay in steel delivery does.

Common mistakes with the critical path

The critical path and Trakend

Trakend's Gantt schedule has finish-to-start links with lag days. When you move a task, the linked tasks after it move with it, and you can save a baseline and see how many tasks are behind it. Trakend does not calculate or highlight a critical path or float. If your contract requires CPM analysis, keep that in your scheduling program and upload the schedule as a PDF to the project so the field can see it. See Gantt chart schedule.

Related terms

The detailed short-term plan drawn from the schedule is the look-ahead schedule. The contract finish date the path is measured against is usually substantial completion. Late answers in the RFI log are a common cause of critical delays.

Frequently asked questions

What is float?

The number of days an activity can be delayed without delaying the project finish. Activities on the critical path have zero float.

Can a schedule have more than one critical path?

Yes. Two or more chains can be equally long, and near-critical chains can become critical as the job goes on.

Why does the critical path matter for delay claims?

Because a delay generally extends the job only if it hits critical work. Showing that is a large part of any time extension request.

Related

Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state