Committed cost
Committed cost is money a job has already promised to spend, even though the bills have not arrived. It comes from signed subcontracts, issued purchase orders and approved subcontractor change orders.
Last updated
What committed cost is
Actual cost shows only what has been invoiced or paid so far. That makes a job look healthier than it is. If you have signed a subcontract for two hundred thousand dollars and received invoices for thirty thousand, the other one hundred and seventy thousand is not available. It is committed.
A useful budget report therefore has at least four columns for each cost code: budget, committed, actual, and what remains after both. The remaining number is what tells a project manager whether there is still room to buy anything.
Committed cost on a real job
A general contractor budgets ninety thousand dollars for doors, frames and hardware. The project manager issues a purchase order to the supplier for eighty-four thousand. Nothing has been delivered or invoiced, so actual cost is zero. A report that shows only actual cost says ninety thousand is left. The committed column tells the truth: six thousand is left, and the installer has not been hired yet.
Common mistakes with committed cost
- Buying by phone or email with no purchase order, so the commitment exists nowhere in the records.
- Not updating the commitment when a subcontractor change order is approved.
- Counting an invoice as new cost without reducing the open commitment it was billed against.
- Leaving old purchase orders open after the vendor has finished, which overstates what is committed.
- Looking only at actual cost when deciding whether a job is on budget.
Committed cost in Trakend
In Trakend, committed cost comes from purchase orders once they are sent, approved or executed, from approved subcontractor schedules of values, and from approved subcontractor change orders. A purchase order with line items spreads its amount across the cost codes on those lines. The project budget shows committed next to budget, actual and remaining for each cost code. See purchase orders and construction budget.
Related terms
Commitments are tracked by cost code. Actual cost plus open commitments is the starting point for the cost to complete. A subcontractor's change order raises the commitment to that subcontractor.
Frequently asked questions
Is committed cost the same as actual cost?
No. Actual cost has been invoiced or paid. Committed cost has been promised in a subcontract or purchase order. As invoices come in, committed turns into actual.
Why track committed cost?
Because it shows how much of the budget is already spoken for. A job can look under budget on actual cost and still have no money left to buy anything.
Does labor count as committed cost?
Usually not. Your own crew’s labor is tracked as it is worked. Commitments normally cover subcontracts and purchases.
Related
- Purchase orders: Write purchase orders with line items and cost codes, get them approved, email the PDF to the vendor, and match vendor invoices against each order.
- Budget: Set a job budget by cost code, then watch committed, actual and remaining money update as purchase orders, invoices and expenses are approved.
- Job costing: See budget, committed, spent, projected and remaining cost for every cost code on a job. Actual cost comes from approved invoices, expenses and rentals.
- Cost code: A cost code is a short code that sorts every job cost into a category of work, so budget and actual cost can be compared. Example and mistakes.
- Cost to complete: Cost to complete is the estimate of what a job still has to spend to finish. See how it is worked out, an example and the common mistakes.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state