Committed cost

Committed cost is money a job has already promised to spend, even though the bills have not arrived. It comes from signed subcontracts, issued purchase orders and approved subcontractor change orders.

Last updated

What committed cost is

Actual cost shows only what has been invoiced or paid so far. That makes a job look healthier than it is. If you have signed a subcontract for two hundred thousand dollars and received invoices for thirty thousand, the other one hundred and seventy thousand is not available. It is committed.

A useful budget report therefore has at least four columns for each cost code: budget, committed, actual, and what remains after both. The remaining number is what tells a project manager whether there is still room to buy anything.

Committed cost on a real job

A general contractor budgets ninety thousand dollars for doors, frames and hardware. The project manager issues a purchase order to the supplier for eighty-four thousand. Nothing has been delivered or invoiced, so actual cost is zero. A report that shows only actual cost says ninety thousand is left. The committed column tells the truth: six thousand is left, and the installer has not been hired yet.

Common mistakes with committed cost

Committed cost in Trakend

In Trakend, committed cost comes from purchase orders once they are sent, approved or executed, from approved subcontractor schedules of values, and from approved subcontractor change orders. A purchase order with line items spreads its amount across the cost codes on those lines. The project budget shows committed next to budget, actual and remaining for each cost code. See purchase orders and construction budget.

Related terms

Commitments are tracked by cost code. Actual cost plus open commitments is the starting point for the cost to complete. A subcontractor's change order raises the commitment to that subcontractor.

Frequently asked questions

Is committed cost the same as actual cost?

No. Actual cost has been invoiced or paid. Committed cost has been promised in a subcontract or purchase order. As invoices come in, committed turns into actual.

Why track committed cost?

Because it shows how much of the budget is already spoken for. A job can look under budget on actual cost and still have no money left to buy anything.

Does labor count as committed cost?

Usually not. Your own crew’s labor is tracked as it is worked. Commitments normally cover subcontracts and purchases.