WIP report (work in progress schedule)
A WIP report, short for work in progress, is an accounting schedule that lists every open job and compares how much of it is complete, how much revenue has been earned and how much has been billed. It shows whether each job is overbilled or underbilled.
Last updated
What a WIP report is
For each job the schedule usually shows the contract amount including approved change orders, the estimated total cost, the cost to date, the percent complete, the revenue earned, the amount billed, and the difference between earned and billed.
Percent complete is most often cost to date divided by estimated total cost. Earned revenue is the contract amount times that percentage. If you have billed more than you have earned, the job is overbilled. If you have billed less, it is underbilled. Banks, bonding companies and accountants read the WIP report closely because it shows the real position of a contractor's open work.
A WIP report on a real job
A contractor has a job with a contract of one million dollars and an estimated cost of eight hundred thousand. Cost to date is four hundred thousand, so the job is half complete and five hundred thousand of revenue is earned. The contractor has billed five hundred and sixty thousand. The job is overbilled by sixty thousand. That is good for cash today, but it is money for work that still has to be done.
Common mistakes with WIP reports
- Never updating the estimated total cost, so percent complete is wrong on every job that is over budget.
- Leaving approved change orders out of the contract amount.
- Counting unapproved change orders as if they were certain.
- Treating overbilling as profit instead of as work still owed.
- Preparing the schedule once a year for the accountant instead of every month for yourself.
WIP reports and Trakend
Trakend does not produce a WIP report. It is a project tool, not an accounting system. What it does give your accountant is the job-side numbers a WIP schedule is built from: the contract amount with approved change orders, the amount billed on pay applications, cost to date by cost code, open commitments and the projected cost. Approved billing and costs can also be sent to QuickBooks. See job costing and QuickBooks Online sync.
Related terms
The schedule depends on an honest cost to complete. Its billing column comes from each pay application, and its cost columns from cost codes and committed cost.
Frequently asked questions
What does overbilled mean?
You have billed more than the revenue you have earned based on percent complete. Accountants show it as a liability, because you owe that work.
What does underbilled mean?
You have earned more than you have billed. It can mean slow billing, unapproved changes, or a job whose cost estimate is too low.
Who asks for a WIP report?
Bonding companies, banks and outside accountants. Well-run contractors also review one every month for their own use.
This page is general information, not accounting or tax advice. Ask your accountant how these terms apply to your books.
Related
- Job costing: See budget, committed, spent, projected and remaining cost for every cost code on a job. Actual cost comes from approved invoices, expenses and rentals.
- Cost to complete: Cost to complete is the estimate of what a job still has to spend to finish. See how it is worked out, an example and the common mistakes.
- Committed cost: Committed cost is money a job has promised to spend through purchase orders and subcontracts but has not yet been billed. Example and mistakes.
- QuickBooks Online sync: Two-way sync between Trakend and QuickBooks Online: approved pay apps, bills, POs, expenses and time go over, and payment status comes back.
- Pay application: A pay application is the contractor’s periodic request for payment, based on work completed against the schedule of values. Example and mistakes.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state