Backcharge
A backcharge is a cost that one party takes back from another because of something the second party did or failed to do. Most often a general contractor deducts it from a subcontractor's payment to cover damage, cleanup or corrective work.
Last updated
What a backcharge is
Typical reasons are damage to another trade's finished work, trash left behind that someone else had to haul, defective work that was fixed by others, or supplies and equipment the general contractor provided that the subcontractor was supposed to bring.
A fair backcharge follows a pattern. The problem is documented when it is found. The responsible party is told in writing and given a chance to fix it themselves, as the subcontract requires. Only if they do not is the work done by others and the real cost deducted. A backcharge that appears as a surprise on a check stub usually starts a dispute.
A backcharge on a real job
A flooring crew finds drywall mud dropped across a finished concrete floor that is about to receive polished sealer. The superintendent photographs it, emails the drywall subcontractor that morning, and gives them until the next day to clean it. Nobody comes. The general contractor pays a laborer six hours to scrape and clean, and sends the drywall subcontractor a written backcharge with the photos, the notice and the labor cost.
Common mistakes with backcharges
- Deducting money with no written notice and no chance to fix the problem.
- No photos or dates, so it becomes one person's word against another's.
- Charging a round number instead of the actual cost with backup.
- Waiting until final payment to bring up a problem from six months ago.
- For subcontractors: ignoring a backcharge notice instead of answering in writing right away.
Backcharges and Trakend
Trakend does not have a form called a backcharge. What it gives you is the evidence and the paper trail. Photos keep their date and location, the daily report records what was found and who was told, and messages and punch list items show the notice and the response. The money is then handled as a deduct on a change order. See construction photos and change orders.
Related terms
A backcharge is often written up as a deduct change order. The proof usually comes from the daily report and the punch list. It reduces what is paid on the pay application.
Frequently asked questions
Can a general contractor backcharge without notice?
That depends on the subcontract. Most require written notice and a chance to correct the problem first. Backcharges made without notice are much harder to defend.
How does a subcontractor dispute a backcharge?
Answer in writing right away, ask for the backup, and give your own photos and daily reports. Do not wait for final payment.
Is a backcharge the same as a deduct change order?
A deduct change order is one way to record it. The backcharge is the claim. The change order is the paperwork that adjusts the subcontract amount.
This page is general information, not legal, tax or insurance advice. Your contract and your state’s laws decide what applies on your job.
Related
- Change order: A change order is a signed agreement that changes the contract scope, price or time. See an example, common mistakes and how change orders are tracked.
- Punch list: A punch list is the list of small items that must be fixed or finished before a job is accepted as complete. Example, mistakes and related terms.
- Photos: Jobsite photos that sort themselves by day or by daily report, with the date taken, GPS, tags, markups and comments. Download any set as a zip.
- Change orders: Price change orders with your own overhead and profit rules, keep owner and sub change orders in separate logs, and bill them on the next pay app.
- Daily report: A construction daily report records each day on site: weather, crews, hours, work done, deliveries and delays. Example, mistakes and related terms.