Allowance
An allowance is an amount of money included in the contract price for an item that has not been fully decided or defined when the contract is signed. When the real cost is known, the contract is adjusted up or down by the difference.
Last updated
What an allowance is
Owners often want a firm price before every choice is made. An allowance lets the contract move ahead. The documents might say to include a set sum for lobby light fixtures, for landscaping, or for removing unsuitable soil. The contractor carries that number in the bid.
The contract should say what the allowance covers. Does it include only the material, or also labor, freight, tax, overhead and profit? When the item is finally selected and priced, the actual cost is compared with the allowance and a change order settles the difference.
An allowance on a real job
A tenant build-out contract carries an allowance of twenty thousand dollars for reception desk millwork, because the design is not finished. Two months later the owner picks a desk that the millwork shop prices at twenty-six thousand installed. The contractor shows the quote, and a change order adds six thousand dollars. Had the desk come in at seventeen thousand, a deduct change order would have returned three thousand to the owner.
Common mistakes with allowances
- Not spelling out whether labor, tax, freight and markup are inside the allowance.
- Spending past the allowance without telling the owner until the bill arrives.
- Treating an allowance as a not-to-exceed budget. It is an estimate that gets trued up.
- Losing track of what has been spent against each allowance.
- Forgetting to credit the owner when the item costs less.
Allowances and Trakend
Trakend does not have a special allowance tracker. Contractors usually handle one as its own line on the schedule of values and its own cost code in the budget, so the spending against it is easy to see. When the real cost is known, the difference is written as an add or deduct change order, which then lands on the next pay application. See schedule of values and construction budget.
Related terms
The true-up is done with a change order. Allowances appear as lines on the schedule of values and are most common in a lump sum contract. Tracking the spending uses a cost code.
Frequently asked questions
Is an allowance the same as a contingency?
No. An allowance is for a known item whose cost is not yet fixed. A contingency is money set aside for things nobody can foresee.
What happens if the cost is less than the allowance?
The owner normally gets the difference back through a deduct change order.
Does an allowance include overhead and profit?
Only if the contract says so. Many contracts state that the contractor’s overhead and profit on the allowance amount are already in the base price.
Related
- Change order: A change order is a signed agreement that changes the contract scope, price or time. See an example, common mistakes and how change orders are tracked.
- Schedule of values: A schedule of values breaks the contract price into line items that add up to the total and is used to bill each month. Example and common mistakes.
- Lump sum contract: A lump sum contract sets one fixed price for a defined scope of work. See an example, common mistakes, and how it differs from unit price work.
- Schedule of values: Build a schedule of values by hand or from your cost-code budget, set retainage per line, get it approved once, and bill from it every month.
- Budget: Set a job budget by cost code, then watch committed, actual and remaining money update as purchase orders, invoices and expenses are approved.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state