Steel erection JHA template

A job hazard analysis for structural steel and metal deck crews. It follows OSHA 29 CFR 1926 Subpart R: site readiness, hoisting and landing members, connecting and bolting, decking, and field welding.

Last updated

When to use this JHA

Use this JHA for setting columns, beams, joists and deck. Steel erection has its own fall protection heights and its own rules for hoisting, so do not copy a general fall protection JHA. Start with the written notice that the concrete and anchor bolts are ready for steel.

Job steps, hazards and controls

Job stepHazardsControls
Confirm site readiness and the erection planCollapse from unready foundations; poor accessWritten notice that concrete has reached strength and anchor bolts are ready (1926.752); site-specific erection plan; crane access set
Hoist and land membersStruck by loads; caught-betweenPre-shift rigging inspection; tag lines; no work under suspended loads except connectors; multiple-lift rigging per 1926.753
Connect and boltFalls from height; falling bolts and toolsFall protection above 15 ft (connectors above 30 ft / two stories); at least two bolts per connection before release; tool lanyards
Place deckingFalls through openings and deck edges; windControlled decking zone rules; covers on openings; secure bundles; stop work in high wind
Field weld / cutBurns; fire; fumesHot work permit + fire watch; fire extinguisher within reach

Hazards to list for steel erection

Controls to put in place

PPE, permits and training

What crews most often miss

Stability during erection is the quiet hazard. A column or beam is only safe once it is bolted or braced the way the erection plan calls for. Do not release the hoist line early to speed up the crane. Below the steel, keep other trades out from under the work and control dropped bolts and tools with lanyards and barricades.

How to use this template

  1. Walk the work area first and compare what you see with the steel erection steps above.
  2. Add any hazard you find that is not listed, and cross out steps that do not apply today.
  3. Review it out loud with the crew. Ask what they would add.
  4. Have everyone sign in below, and update the JHA if the work or the conditions change.

Fill out this JHA in Trakend

In Trakend, a steel erection JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.

Crew sign-in

Print name · Signature · Time in · Time out

Frequently asked questions

What is the fall protection height for steel erection?

Under OSHA 29 CFR 1926 Subpart R, most steel erection work needs fall protection above 15 feet. Connectors, and deckers in a controlled decking zone, have special rules between 15 and 30 feet or two stories.

What has to happen before steel erection starts?

The controlling contractor gives the steel erector written notice that the concrete in footings, piers and walls has reached enough strength and that anchor bolts have been repaired or replaced as needed.

This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.