Heavy equipment, cranes and rigging JHA template
A job hazard analysis for lifts with cranes and other heavy equipment. It covers inspection of the machine and rigging, setup and travel route, operating and swinging, rigging and signaling, and landing the load.
Last updated
When to use this JHA
Use this JHA for crane picks, boom truck deliveries, setting equipment and any lift where a load goes over or near people. For critical lifts, attach the lift plan. The cranes standard, OSHA 29 CFR 1926 Subpart CC, sets the rules for power line clearance, signal persons and riggers.
Job steps, hazards and controls
| Job step | Hazards | Controls |
|---|---|---|
| Pre-use inspection of equipment and rigging | Mechanical failure; damaged slings or hooks | Equipment pre-use checklist done; rigging inspected and tagged with capacity; remove damaged gear from service |
| Plan the lift / travel route and set up | Overturning; ground failure; power line contact | Firm, level ground and outrigger pads; lift plan for critical lifts; keep 20 ft from power lines up to 350 kV (cranes, 1926.1408) |
| Operate, travel and swing | Struck-by / caught-between swing radius; run-over | Barricade the swing radius; spotter for backing equipment; seat belts; 3-point contact getting on and off |
| Rig and signal the load | Dropped load; pinch points; miscommunication | Qualified rigger and signal person; tag lines; one designated signal person; stay clear of suspended loads |
| Land and unhook the load | Load shifting; caught-between | Land on cribbing; hands off pinch points; release only when the load is stable |
Hazards to list for crane lifts, rigging and heavy equipment moves
- Vehicle/equipment movement
- Moving machinery/equipment
- Struck-by hazards
- Caught-in/between
- Overhead hazards
- Electrical hazards
- Noise exposure
- Structural collapse
- Suspended loads
- Equipment rollover
- Slips/trips
Controls to put in place
- Spotter for backing equipment
- Barricade the swing radius
- Stay clear of suspended loads
- Hearing protection in high-noise areas
- Rigging inspected before each use
- Qualified rigger and signal person
- Keep 20 ft from overhead power lines
- Pre-task briefing with crew
- Keep walkways clear (housekeeping)
PPE, permits and training
- Standard site PPE: Hard hat, Safety glasses (ANSI Z87.1), Steel-toed boots, High-visibility vest, Safety gloves.
- Added for crane lifts, rigging and heavy equipment moves: Ground spotter for lifts, Barricades/safety cones, Hearing protection (plugs/muffs).
- Permits and plans: Critical Lift Permit
- Training to verify: Crane Operator, Equipment Operation.
What crews most often miss
Ground conditions and power lines are settled before the crane is set up, not after. Find out what is under the outriggers, including buried utilities, vaults and fresh backfill. Name one signal person so the operator only takes signals from one place, with one exception: anyone can give a stop signal.
How to use this template
- Walk the work area first and compare what you see with the crane lifts, rigging and heavy equipment moves steps above.
- Add any hazard you find that is not listed, and cross out steps that do not apply today.
- Review it out loud with the crew. Ask what they would add.
- Have everyone sign in below, and update the JHA if the work or the conditions change.
Fill out this JHA in Trakend
In Trakend, a crane lifts, rigging and heavy equipment moves JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.
Crew sign-in
Print name · Signature · Time in · Time out
Frequently asked questions
How far must a crane stay from power lines?
Under OSHA 1926.1408, if you do not know the line voltage, keep every part of the crane, load line and load at least 20 feet away for lines up to 350 kV. With the voltage confirmed by the utility, the minimum distances in Table A apply.
Who can rig and signal a load?
A qualified rigger must rig the load and a qualified signal person must give signals when the operator cannot see the load or the path. Both are defined in OSHA 29 CFR 1926 Subpart CC.
This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.
Related
- Crane and rigging safety: Free 5-minute crane and rigging toolbox talk: load weight, rigging inspection, signal person, power lines, tag lines and staying out from under loads.
- Steel erection: Free steel erection JHA: site readiness and anchor bolts, hoisting, connecting and bolting, decking, field welding, and fall protection for ironworkers.
- Steel erectors: Software for steel erectors: erection JHAs, crane-day paperwork, daily reports by sequence, RFIs for fit-up problems, T&M tickets and pay apps.
- Working near utilities: Free 5-minute toolbox talk on underground and overhead utilities: 811 locates, hand digging near marks, power line clearance and what to do after a strike.