Heavy equipment, cranes and rigging JHA template

A job hazard analysis for lifts with cranes and other heavy equipment. It covers inspection of the machine and rigging, setup and travel route, operating and swinging, rigging and signaling, and landing the load.

Last updated

When to use this JHA

Use this JHA for crane picks, boom truck deliveries, setting equipment and any lift where a load goes over or near people. For critical lifts, attach the lift plan. The cranes standard, OSHA 29 CFR 1926 Subpart CC, sets the rules for power line clearance, signal persons and riggers.

Job steps, hazards and controls

Job stepHazardsControls
Pre-use inspection of equipment and riggingMechanical failure; damaged slings or hooksEquipment pre-use checklist done; rigging inspected and tagged with capacity; remove damaged gear from service
Plan the lift / travel route and set upOverturning; ground failure; power line contactFirm, level ground and outrigger pads; lift plan for critical lifts; keep 20 ft from power lines up to 350 kV (cranes, 1926.1408)
Operate, travel and swingStruck-by / caught-between swing radius; run-overBarricade the swing radius; spotter for backing equipment; seat belts; 3-point contact getting on and off
Rig and signal the loadDropped load; pinch points; miscommunicationQualified rigger and signal person; tag lines; one designated signal person; stay clear of suspended loads
Land and unhook the loadLoad shifting; caught-betweenLand on cribbing; hands off pinch points; release only when the load is stable

Hazards to list for crane lifts, rigging and heavy equipment moves

Controls to put in place

PPE, permits and training

What crews most often miss

Ground conditions and power lines are settled before the crane is set up, not after. Find out what is under the outriggers, including buried utilities, vaults and fresh backfill. Name one signal person so the operator only takes signals from one place, with one exception: anyone can give a stop signal.

How to use this template

  1. Walk the work area first and compare what you see with the crane lifts, rigging and heavy equipment moves steps above.
  2. Add any hazard you find that is not listed, and cross out steps that do not apply today.
  3. Review it out loud with the crew. Ask what they would add.
  4. Have everyone sign in below, and update the JHA if the work or the conditions change.

Fill out this JHA in Trakend

In Trakend, a crane lifts, rigging and heavy equipment moves JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.

Crew sign-in

Print name · Signature · Time in · Time out

Frequently asked questions

How far must a crane stay from power lines?

Under OSHA 1926.1408, if you do not know the line voltage, keep every part of the crane, load line and load at least 20 feet away for lines up to 350 kV. With the voltage confirmed by the utility, the minimum distances in Table A apply.

Who can rig and signal a load?

A qualified rigger must rig the load and a qualified signal person must give signals when the operator cannot see the load or the path. Both are defined in OSHA 29 CFR 1926 Subpart CC.

This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.