How to write a construction daily report
A daily report is the written record of what happened on a jobsite on one day: who was there, what they did, what the weather was, and what got in the way. This guide shows what to put in it and how to make it a five-minute habit.
Last updated
How to fill out a daily report, step by step
- Start with the basics Write the project name, the date, and your name. One report per project per day.
- Record the weather Note the temperature, wind and rain for the morning and the afternoon. If weather stopped or slowed work, say how many hours were lost.
- List every crew For your own crews and each subcontractor, write the company, the number of workers, the hours worked and what they worked on.
- Describe the work Say what was done and where, by area, floor or gridline. Use numbers when you have them: footage, yards, units, rooms.
- Log deliveries and equipment Write down materials delivered, anything that arrived short or damaged, and the major equipment on site, including equipment that sat idle.
- Note visitors and inspections List inspectors, owner's representatives, architects and other visitors, and the result of each inspection.
- Write down delays and problems This is the most important part. Record what held up the work, who was told, and when. Stick to facts.
- Add photos, then send it Attach photos of progress and of anything unusual. Sign or submit the report the same day and send it to the people who need it.
Why the daily report matters
On a good day, nobody reads the daily report. Months later, when there is a dispute over a delay, an injury claim, a backcharge or a warranty problem, it is the first thing everyone asks for. A report written that day by the person who was there carries far more weight than anyone's memory.
It also helps right now. The project manager can see progress without driving to the site. The office can check crew hours against time cards. The owner gets a regular, professional update.
Who writes it, and when
On the general contractor's side, the superintendent usually writes the daily report. Subcontractor foremen write one for their own crew. Many contracts require both.
Write it before you leave the site, or at the latest that evening. A report written on Friday for the whole week is a guess, and it reads like one. If you jot notes on your phone during the day, the report takes a few minutes at the end.
What to include
- Project, date and who wrote the report
- Weather, morning and afternoon, and any hours lost to it
- Each crew: company, headcount, hours and work performed
- Work completed, with locations and quantities
- Materials delivered and equipment on site
- Visitors, inspections and test results
- Delays, problems and instructions received, with names and times
- Safety: toolbox talk held, incidents, near misses
- Photos
Common mistakes
- Writing "same as yesterday". Every day needs its own facts.
- Leaving out the bad news. Delays and problems are exactly what the report is for.
- Opinions and blame. Write "Area B was not released until 1 pm" instead of "the GC messed up again".
- No locations. "Installed pipe" tells nobody anything. "Installed 120 feet of 8-inch storm line from MH-3 to MH-4" does.
- Photos with no date or description, sitting on one person's phone.
Doing daily reports in Trakend
In Trakend the daily report is one screen on a phone. Weather for the date fills in by itself from the project's zip code. You add crews from your roster and the man-hours are added up for you. Photos attach to the day. If you plan crews in the weekly planner, tomorrow's report starts with those crews already filled in.
When the day is done, Finalize Day gathers the daily report, the JHAs, the toolbox talks and any incident reports into one PDF with your logo and emails it to the project's distribution list. See daily reports in Trakend.
Frequently asked questions
Is a daily report the same as a daily log?
Yes. Daily report, daily log, daily construction report and superintendent's report are different names for the same record.
How long should a daily report take?
About five to ten minutes if you do it every day. It takes longer when you try to rebuild several days from memory.
Should subcontractors write their own daily reports?
Yes. A subcontractor's report records its own crew, work and delays, which the general contractor's report may not cover in detail. Many subcontracts require one.
Can a daily report be changed later?
Corrections should be made openly, with a note of what changed and when. Rewriting old reports hurts their value as a record.
Related
- Daily reports: Fill out construction daily reports on a phone: auto weather, crews and man-hours, photos, delays. Finalize the day and email a branded PDF.
- How to run a toolbox talk: How to run a toolbox talk: pick the topic, keep it to five minutes, get the crew talking, and document who attended. A simple guide for foremen.
- Site sign-in sheets: How to run a construction site sign-in sheet: what to collect, where to put it, how to handle visitors and subs, and how to keep the records.
- Change order vs T&M ticket: Change order vs T&M ticket: a change order changes the contract price, a T&M ticket records extra work as it happens. How to use both to get paid.
- Trades: See how Trakend fits your trade: concrete, earthwork, electrical, plumbing, HVAC, roofing, framing, steel, paving, utilities and more.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state