Rebar placers work between the detailer, the fabricator and the pour schedule. Trakend helps reinforcing steel contractors record tons placed, inspections passed and every late revision that changes the mat.
Last updated
Squeezed between fabrication and the pour
The rebar crew gets the deck after the formwork is ready and has to be done before the pump shows up. Fabricated steel has to arrive in the right sequence, tagged for the right pour. A missing bundle or a wrong bend stops the crew and puts the pour at risk.
Revisions also land on the placer. Added bars, changed spacing and new openings arrive after the steel is fabricated, sometimes after it is tied.
JHAs and toolbox talks for ironworkers placing rebar
Rebar placing shares the pour-day hazards in the concrete pour JHA, and adds its own.
- Impalement on exposed bar ends: caps or troughs
- Backs and hands: carrying and tying all day. See the lifting talk
- Walking on mats and across decks
- Bundles hoisted by crane: rigging and tag lines
- Wall and column cages that can tip before they are braced
- Falls at deck edges and from wall forms
What goes on a rebar daily report
Pour by pour.
- Placers and hours
- Areas placed: footings, walls, columns and deck, by pour number
- Tons or bundles placed, noted in the work description
- Deliveries from the fabricator, with photos of bundle tags
- Missing or misfabricated bars, and what was done
- Inspections: special inspector on site, pass or corrections
- Waiting on formwork, embeds or other trades
- Photos of every mat before the pour
Inspection records and pre-pour photos
Before the pour, photograph the mat with a tape showing spacing and clearance, and note the inspector's name and the result in the daily report. If corrections were required, record that they were made. Once the concrete is placed, this is the only record of what is inside it.
Revisions, T&M and billing
When a revision adds or moves bars after fabrication, the extra labor is real: sorting, cutting, re-tying, sometimes pulling steel out. Record it on a T&M ticket with hours and material, signed on screen. For larger revisions, price a change order with your markups.
Bill by pour, level or tonnage from the schedule of values. Stored materials cover fabricated steel delivered to the site, and retainage is tracked on each line.
Crews and equipment
Placers clock in on a phone or kiosk tablet in the job's GPS fence, and time-clock-only crew members are free. Track benders, cutters, tying tools and trucks in the equipment list.
Flat pricing, every feature
You pay by plan, not by head: Starter is $299 a month for 5 users, Team is $749 for 20, Business is $1,299 for 50, Pro is $1,999 for 100, and Unlimited is $2,499. Nothing is held back for higher plans, and workers who only clock in are free. Rebar and reinforcing steel contractors can start with a 30-day free trial. See pricing.
Frequently asked questions
Can I record tons placed per pour?
Yes. Note tons or bundles by pour in the daily report's work description, with photos of the bundle tags.
How do I document a rebar inspection?
Record the inspector, the result and any corrections in the daily report's inspections field, with photos of the mat before the pour.
Can I bill for labor caused by late drawing revisions?
Record the extra hours and material on a T&M ticket, get it signed, and convert it into a change order.
Related
- Concrete pour and finishing: Free concrete pour and finishing JHA: rebar, ready-mix trucks, pump hose whip, wet concrete burns and power trowels, with controls and a crew sign-in.
- Concrete contractors: Software for concrete contractors: pour-day JHAs, daily reports with crews and weather, crew time clock, T&M tickets, change orders and pay apps.
- Back injury prevention and lifting: Free 5-minute safe lifting toolbox talk: planning the lift, keeping the load close, team lifts, carts and hoists, and avoiding the twist.
- Heavy equipment, cranes and rigging: Free crane, rigging and heavy equipment JHA: pre-use inspection, ground and outriggers, power line clearance, swing radius, rigging and signals.
- Daily reports: Fill out construction daily reports on a phone: auto weather, crews and man-hours, photos, delays. Finalize the day and email a branded PDF.
- Change orders & pay apps: Change orders with OH&P markup, field-signed T&M tickets, schedule of values, retainage, and G702/G703-style pay application PDFs.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state