Construction software for foundation and drilled pier contractors
Deep foundation work is paid by the foot and decided by what the drill finds. Trakend helps pier and foundation contractors record each shaft, each pour and each obstruction the day it happens.
Last updated
Paid by the foot, argued by the foot
A drilled pier contractor's contract is built on quantities: so many piers at so many feet. The ground then decides the real numbers. Piers go deeper to reach bearing. Holes cave and need casing. The rig hits rock, old foundations or water.
Each of those changes the footage, the concrete volume and the time, and each has to be agreed with the inspector on site that day. A missing pier log is a missing invoice.
JHAs for drill rigs and pier work
Pier work combines a drill rig, a crane, open holes and concrete. Start from the cranes and rigging JHA and the concrete pour JHA.
- Open shafts: covers and barricades
- Rotating kelly bar and auger: stay clear
- Rig and crane setup on soft or uneven ground
- Overhead power lines near the mast and boom
- Setting rebar cages with a crane
- Underground utilities: a current locate before drilling. See the utilities talk
What goes on a pier daily report
A line for every shaft.
- Crew, operators and hours
- Piers drilled: number, diameter, planned depth and actual depth
- What was found: rock, water, caving, obstructions
- Casing used, and how much
- Cage set and inspected, concrete placed, and truck tickets photographed
- Inspector or geotechnical engineer on site, and what was approved
- Rig downtime and standby, with the cause
- Weather
Getting the inspector's sign-off the same day
When the engineer directs a pier deeper, or accepts bearing at a different depth, write it into the daily report with the name and time. Send the report that evening with Finalize Day, so the general contractor has the same record you do. Overruns that were directed in the field are much easier to bill when they were reported the same day.
Obstructions, standby and unit-price billing
Obstructions and standby are the classic deep foundation extras. Write a T&M ticket for rig time, crew time and tooling while it is happening, and have it signed on screen.
Set up the schedule of values with lines for mobilization, piers by diameter, casing and extra depth, and bill by dollar amount as footage is completed. Approved change orders are added to the next pay application, and retainage is tracked.
Rigs, cranes and tooling
Track drill rigs, cranes, augers, core barrels, casing and pumps in the equipment list, with service due by hour meter, inspection logs and rental return dates. Crews clock in by phone or kiosk tablet in the job's GPS fence.
Flat pricing, every feature
You pay by plan, not by head: Starter is $299 a month for 5 users, Team is $749 for 20, Business is $1,299 for 50, Pro is $1,999 for 100, and Unlimited is $2,499. Nothing is held back for higher plans, and workers who only clock in are free. Foundation and drilled pier contractors can start with a 30-day free trial. See pricing.
Frequently asked questions
Can I keep a pier log in the daily report?
Yes. List each pier with its diameter, planned and actual depth, conditions found and concrete placed in the work description, and attach photos. For a signed record, use a checklist for each shaft.
How do I bill extra depth?
Record the directed depth and who directed it in the daily report, then bill it on your unit-price line for extra depth or as a change order, depending on your contract.
Can I record rig standby?
Yes. Put standby hours for the rig and crew on a T&M ticket and get it signed on screen.
Related
- Heavy equipment, cranes and rigging: Free crane, rigging and heavy equipment JHA: pre-use inspection, ground and outriggers, power line clearance, swing radius, rigging and signals.
- Concrete pour and finishing: Free concrete pour and finishing JHA: rebar, ready-mix trucks, pump hose whip, wet concrete burns and power trowels, with controls and a crew sign-in.
- Working near utilities: Free 5-minute toolbox talk on underground and overhead utilities: 811 locates, hand digging near marks, power line clearance and what to do after a strike.
- Concrete contractors: Software for concrete contractors: pour-day JHAs, daily reports with crews and weather, crew time clock, T&M tickets, change orders and pay apps.
- Daily reports: Fill out construction daily reports on a phone: auto weather, crews and man-hours, photos, delays. Finalize the day and email a branded PDF.
- Change orders & pay apps: Change orders with OH&P markup, field-signed T&M tickets, schedule of values, retainage, and G702/G703-style pay application PDFs.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state