A job hazard analysis for installing water, sewer, storm, gas and conduit underground. It covers locating existing lines, the trench, setting pipe and structures, tie-ins, and testing and backfill.

Last updated

When to use this JHA

Use this JHA for pipe crews and duct bank crews. Utility work stacks several serious hazards in one place: a trench that can cave in, loads swinging over the trench, live lines nearby, and manholes or vaults that can hold bad air. Go through each one before the day starts.

Job steps, hazards and controls

Job stepHazardsControls
Verify 811 locates and pothole existing linesStrike of live gas, electric or fiberValid 811 ticket; hand-dig/vacuum excavate within the tolerance zone; owner standby for critical lines
Excavate and protect the trenchCave-in; struck-by equipmentProtective system at 5 ft or deeper; competent person inspection; ladder within 25 ft
Lower and set pipe or structuresStruck by swinging or dropped loads; caught-between pipe and trench wallRated rigging inspected; tag lines; stay clear of suspended loads; workers out of the trench while the load is lowered into position
Connect to existing systems / tie-insHazardous atmosphere in manholes; stored pressure; sewage (biological)Gas monitor before entry; confined space permit where required; isolate and depressurize lines; hand washing and gloves
Test, backfill and restorePressure-test failure; caught-between compaction equipmentExclusion zone during pressure tests; remove workers before backfill

Hazards to list for underground utility work

Controls to put in place

PPE, permits and training

What crews most often miss

The tie-in is where routine days go wrong. Before anyone connects to an existing system, confirm the line is isolated and has no pressure, and test the air before entering a manhole or vault. During pressure tests, clear people away from caps, plugs and fittings. And keep workers out of the trench while pipe or structures are lowered in.

How to use this template

  1. Before the crew starts, look at the actual work area and check it against the steps listed for underground utility work.
  2. Add any hazard you find that is not listed, and cross out steps that do not apply today.
  3. Review it out loud with the crew. Ask what they would add.
  4. Have everyone sign in below, and update the JHA if the work or the conditions change.

Fill out this JHA in Trakend

In Trakend, a underground utility work JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.

Crew sign-in

Print name · Signature · Time in · Time out

Frequently asked questions

What is potholing?

Carefully digging by hand or with vacuum excavation to expose an existing buried line so you can see exactly where it is and how deep it is before digging near it with a machine.

When is a manhole a confined space?

Manholes, vaults and similar structures have limited ways in and out and are not designed for people to stay in. If they have or could have a hazard such as bad air, they must be treated as permit-required confined spaces under OSHA 29 CFR 1926 Subpart AA.

This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.