Trenching and excavation JHA template
A job hazard analysis for digging and working in trenches and excavations. It follows OSHA 29 CFR 1926 Subpart P: locate utilities, have a competent person inspect, protect the trench, and give people a way out.
Last updated
When to use this JHA
Use this JHA any time a crew will dig a trench or work in one, for footings, utilities, drains or repairs. The rules that matter most are in the steps below: a protective system at 5 feet or deeper, a ladder within 25 feet of workers in trenches 4 feet or deeper, and spoil kept at least 2 feet back from the edge.
Job steps, hazards and controls
| Job step | Hazards | Controls |
|---|---|---|
| Call 811 and verify utility locates before digging | Contact with buried electric, gas or water lines | Valid 811 ticket on site; marks visible; hand-dig / pothole within the tolerance zone |
| Competent person classifies soil and inspects the excavation | Cave-in from unstable soil, water, vibration | Daily trench inspection by the competent person before each shift and after rain or changes |
| Install protective system for trenches 5 ft or deeper | Cave-in / engulfment | Shoring / sloping per competent person (trench box, shoring or sloping per soil type); 20 ft+ deep requires a PE-designed system |
| Excavate and place spoil | Struck-by excavator bucket; falling material into the trench; equipment at the edge | Barricade the swing radius; spoil and materials at least 2 ft back from the edge; stop blocks for equipment near the edge |
| Enter, work in and exit the trench | Cave-in; hazardous atmosphere (over 4 ft deep); falls into the excavation | Ladder within 25 ft in trench (4 ft deep or more); test atmosphere where low oxygen or gases may exist; never work outside the protective system; guardrails or barricades at the edge |
| Backfill and compact | Caught-between compactor; struck-by equipment | Remove workers before backfilling; spotter for equipment; remove protective system from the bottom up |
Hazards to list for trenching and excavation
- Excavation/trenching
- Structural collapse
- Caught-in/between
- Struck-by hazards
- Vehicle/equipment movement
- Falls from height
- Confined spaces
- Electrical hazards
- Buried utilities
- Water accumulation
- Slips/trips
Controls to put in place
- Shoring / sloping per competent person
- Ladder within 25 ft in trench
- Daily trench inspection
- Barricade the swing radius
- Spotter for backing equipment
- Spoil pile at least 2 ft from the edge
- 811 locate verified before digging
- Gas monitor before entry
- Pre-task briefing with crew
- Keep walkways clear (housekeeping)
PPE, permits and training
- Standard site PPE: Hard hat, Safety glasses (ANSI Z87.1), Steel-toed boots, High-visibility vest, Safety gloves.
- Added for trenching and excavation: Barricades/safety cones, Air monitor.
- Permits and plans: Excavation Permit
- Training to verify: Trenching & Shoring, Equipment Operation.
What crews most often miss
Trenches change during the day. Rain, a water leak, vibration from traffic or a truck parked at the edge can turn a safe trench into a dangerous one. The competent person inspects before each shift and again after anything changes, and has the authority to pull everyone out. Nobody goes into an unprotected trench "just for a minute".
How to use this template
- Take this trenching and excavation template to the work area and check each step against real conditions.
- Add any hazard you find that is not listed, and cross out steps that do not apply today.
- Review it out loud with the crew. Ask what they would add.
- Have everyone sign in below, and update the JHA if the work or the conditions change.
Fill out this JHA in Trakend
In Trakend, a trenching and excavation JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.
Crew sign-in
Print name · Signature · Time in · Time out
Frequently asked questions
At what depth does a trench need a protective system?
Under OSHA 29 CFR 1926 Subpart P, trenches 5 feet deep or more need a protective system such as sloping, shoring or a trench box, unless the excavation is entirely in stable rock. A competent person can require protection in a shallower trench if there are signs of a possible cave-in.
Who is the competent person for an excavation?
Someone who can identify existing and predictable hazards in the excavation and who has the authority to correct them right away, including stopping work and removing workers.
This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.
Related
- Trenching and excavation safety: Free 5-minute trenching toolbox talk: protective systems at 5 feet, daily competent person inspections, spoil setback, ladders and 811 locates.
- Working near utilities: Free 5-minute toolbox talk on underground and overhead utilities: 811 locates, hand digging near marks, power line clearance and what to do after a strike.
- Underground utilities: Free underground utility JHA: potholing existing lines, trench protection, setting pipe and structures, tie-ins, manhole entry and pressure tests.
- Excavation and earthwork contractors: Software for excavation and earthwork contractors: trench JHAs, daily reports with equipment and loads, GPS time clock, T&M tickets and pay apps.
- Safety, JHAs & toolbox talks: Digital JHAs with crew sign-in signatures, 89 toolbox talks in English and Spanish, incident reports with OSHA recordable flags, and checklists.
Start a 30-day free trial · Pricing · Features · Free templates · Guides · By trade · By state