Masonry JHA template

A job hazard analysis for block, brick and stone crews. It covers the limited access zone and scaffold, mixing mortar and grout, laying units, cutting, and working from scaffolds.

Last updated

When to use this JHA

Use this JHA for CMU walls, brick veneer and stone. Masonry walls under construction can fall over before they are tied into the structure, which is why OSHA 1926.706 requires a limited access zone and bracing. Set both up before the wall goes up, not after it is tall.

Job steps, hazards and controls

Job stepHazardsControls
Set up the limited access zone and scaffoldWall collapse during construction; scaffold fallsLimited access zone = wall height + 4 ft on the unscaffolded side (1926.706); brace walls over 8 ft until supported; competent person on the scaffold
Mix mortar and groutCement burns; silica dust; mixer caught-inWaterproof gloves; mixer guards; lockout before cleaning the mixer; dust control
Lay block / brickBack strain; dropped units; cutsTeam lift / use dolly over 50 lbs (heavy CMU); gloves; stock material within reach
Cut unitsSilica dust; saw hazardsWet cutting / vacuum dust control per Table 1; face shield; hearing protection
Work from scaffoldsFalls; overloaded planksGuardrails or fall protection above 10 ft; do not overload planks with material

Hazards to list for masonry

Controls to put in place

PPE, permits and training

What crews most often miss

Wind is the hazard masons underestimate. A tall, unbraced wall can come down in a gust, so brace as the wall rises and keep everyone except the masons out of the limited access zone. On the scaffold, watch the weight: pallets of block and tubs of mortar add up quickly, and planks have a limit.

How to use this template

  1. Walk the work area first and compare what you see with the masonry steps above.
  2. Add any hazard you find that is not listed, and cross out steps that do not apply today.
  3. Review it out loud with the crew. Ask what they would add.
  4. Have everyone sign in below, and update the JHA if the work or the conditions change.

Fill out this JHA in Trakend

In Trakend, a masonry JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.

Crew sign-in

Print name · Signature · Time in · Time out

Frequently asked questions

What is a limited access zone in masonry?

An area next to a masonry wall under construction that only the workers building the wall may enter. Under OSHA 1926.706 it runs the length of the wall and extends out the height of the wall plus 4 feet, on the side without scaffolding.

When does a masonry wall need bracing?

OSHA 1926.706 requires masonry walls over 8 feet high to be braced against overturning until permanent supports are in place, unless they are otherwise supported.

This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.