Demolition JHA template

A job hazard analysis for selective and structural demolition. It covers the engineering survey, hazardous material checks, utilities, exclusion zones, the demolition sequence, breaking concrete, and load-out.

Last updated

When to use this JHA

Use this JHA for interior strip-outs, selective demolition and structure removal. Demolition has its own OSHA rules in 29 CFR 1926 Subpart T. The first of them is that a competent person does an engineering survey of the structure before work starts, so the crew knows what is holding up what.

Job steps, hazards and controls

Job stepHazardsControls
Engineering survey and hazardous material checkUnplanned collapse; asbestos, lead, PCBsWritten engineering survey (1926.850); asbestos/lead survey before disturbing materials; stop and report suspect materials
Isolate utilitiesLive electrical, gas, waterLockout/tagout before work; utilities shut off and capped and confirmed
Set up exclusion zones and debris chutesFalling debris onto workers or the publicBarricade drop zones; enclosed chutes for drops over 20 ft; overhead protection at entrances
Demolish selectively, top downStructural collapse; struck-by; falls through openingsFollow the demolition sequence; guardrails / covers on openings; never undermine supports
Break concrete / masonrySilica dust; noise; vibration; flying chipsWet cutting / vacuum dust control; respirator per silica plan; face shield; hearing protection
Load out debrisManual handling; sharp edges; equipment movementTeam lift / use dolly over 50 lbs; cut-resistant gloves; spotter for backing equipment

Hazards to list for demolition

Controls to put in place

PPE, permits and training

What crews most often miss

The unknowns are what hurt people in demolition: a wall that turns out to be load-bearing, a line that is still live, or old material that contains asbestos or lead. If the crew finds something that was not in the survey, or a suspect material, stop and report it. Do not let the schedule decide.

How to use this template

  1. Before the crew starts, look at the actual work area and check it against the steps listed for demolition.
  2. Add any hazard you find that is not listed, and cross out steps that do not apply today.
  3. Review it out loud with the crew. Ask what they would add.
  4. Have everyone sign in below, and update the JHA if the work or the conditions change.

Fill out this JHA in Trakend

In Trakend, a demolition JHA starts with these steps, hazards and controls already filled in. The foreman adjusts it on a phone, the crew signs on the screen with time in and time out, and the signed JHA is saved to the project and added to the day's PDF. See safety features or start a 30-day free trial.

Crew sign-in

Print name · Signature · Time in · Time out

Frequently asked questions

Is an engineering survey required before demolition?

Yes. OSHA 1926.850 requires a competent person to make an engineering survey of the structure before demolition starts, to check the condition of the framing, floors and walls and the chance of an unplanned collapse.

When do we have to check for asbestos or lead?

Before disturbing materials that could contain them, which is common in older buildings. This is normally handled with a survey by a qualified person before demolition begins.

This template is general safety information, not legal advice and not a complete safety program. The employer is responsible for finding the hazards on each site, training workers and meeting OSHA and state requirements. Change it to fit your job before the crew signs.